Implementing Agency: Thirumangalam Municipal Corporation

Segment: Water Supply

Work: The scope of work includes construction of connecting main, pumping main, gravity main, distribution system of 123.106 km, house service connections and related infrastructure development.

End Date: December 22, 2023

Download PDF


Implementing Agency: Agra Development Authority

Segment: Wastewater

Work: The scope of work involves providing design consultancy to address the incompleted stormwater drainage system, coordination with various stakeholders and overseeing the design and development of the drainage system.

End Date: December 27, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of work includes construction of overhead tank (OHT), pump house, clear water reservoir (CWR), repair of existing OHT, laying and jointing of rising main, distribution system, tube-wells, programmable logic controller (PLC) supervisory control and data acquisition (SCADA) automation, commissioning, testing, trial and run, defect liability and related infrastructure.

End Date: December 23, 2023

Download PDF


Implementing Agency: Greater Visakhapatnam Municipal Corporation (GVMC)

Segment: Wastewater

Work: The scope of work includes Hydraulic Analysis using Sewer GEMS software and preparation of environmental site assessment (ESA) and environment and social impact assessment (ESIA) for phase 2 of the project.

End Date: December 15, 2023

Download PDF

Download PDF


Implementing Agency: Uttarakhand Urban Sector Development Agency (UUSDA)

Segment: Water Supply

Work: The scope of work includes development of tubewells, rising main, overhead tank (OHTs), a distribution network of 119 km, sewerage treatment plant (STP) having capacity of 7 millon litres per day (mld), SCADA automation and allied infrastructure with Operation and Maintenance (O&M) of 18 years.

End Date: December 22, 2023

Download PDF


Implementing Agency: Nandgaon Municipal Council

Segment: Water Supply

Work: The scope of work includes project management consultancy (PMC) works for development of water supply scheme (WSS) at Nandgaon in Nashik district, Maharashtra

End Date: December 13, 2023

Download PDF


Implementing Agency: Greater Mumbai Municipal Corporation (MCGM)

Segment: Wastewater

Work: The scope of work includes design, build, operate and construction of SPS having capacity of 10 million litres per day (mld) and allied mechanical, electrical and instrumentation works including Operation and Maintenance (O&M) for three years at harvey Road.

End Date: December 15, 2023

Download PDF


Implementing Agency: Ahmedabad Municipal Corporation (AMC)

Segment: Wastewater

Work: The scope of work includes providing and laying the sewerage trunk main from Narida to Jashodanagar by micro-tunneling method in the AMC area.

End Date: December 14, 2023

Download PDF


Implementing Agency: Rail India Technical and Economic Service (RITES) Limited

Segment: Water Supply

Work: The scope of work includes consultancy services for confirmatory boreholes having maximum length of 500 m including tests recommended for suitable foundation stability for micro tunnelling and conducting electrical resistivity tests for soil strata exploration at 30 locations for Neyyar – PTP nagar transmission main.

End Date: December 14, 2023

Download PDF


Implementing Agency: Chopda Municipal Corporation

Segment: Wastewater

Work: The scope of work includes sewerage and conveyance system for zone- 1,2,3,4 and 6, sewage sup, pump house for IPS – 1 and 2, sewage pumping main, pumping machinery, programmable logic controller (PLC) and supervisory control and data acquisition (SCADA) automation and related infrastructure.

End Date: December 11, 2023

Download PDF


Implementing Agency: Kerala Water Authority (KWA)

Segment: Wastewater

Work: The scope of work includes construction of 5 million litres per day (mld) sewage treatment plant (STP), sewer network and allied components in Panampilly Nagar Zone.

End Date: November 30, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (Urban)

Segment: Wastewater

Work: The scope of work includes investigation, survey, soil investigation and construction of an 18 million litres per day (mld) sewage treatment plant (STP), pre -treatment unit for sewage flow based on sequential batch reactor (SBR) technology, main pumping station (MPS) on well sinking method, intermediate pumping station (IPS) based on well sinking method, rising main, laying of sewer line and trial and run for 3 months.The scope of work includes investigation, survey, soil investigation and construction of an 18 million litres per day (mld) sewage treatment plant (STP), pre -treatment unit for sewage flow based on sequential batch reactor (SBR) technology, main pumping station (MPS) on well sinking method, intermediate pumping station (IPS) based on well sinking method, rising main, laying of sewer line and trial and run for 3 months.

End Date: December 11, 2023

Download PDF


Implementing Agency: Rail India Technical and Economic Service (RITES) Limited

Segment: Wastewater

Work: The scope of work includes detailed topographical survey for 28 km water gravity main for Neyyar – PTP from Neyyar to Trivandrum at an estimated cost of Rs 2.47 million.

End Date: November 25, 2023

Download PDF


Implementing Agency: Karnataka Urban Water Supply And Drainage Board (KUWSDB)

Segment: Water Supply

Work: Lingasugur and Kakkera : The scope of work includes survey, design, construction, supply, installation, testing and commissioning of deep well , water pumpsets in allocated existing jackwell at canal and at existing jackwell, water treatment plant (WTP) – aerator type having capacity of 15.5 million litres per day (mld) and V-wire type having capacity of 12.5 mld, distribution network including supervisory control and data acquisition (SCADA) automation and Operation and Maintenance (O&M) of five years at an estimated cost of Rs 1,173.44 million. The last date for bid submission is November 22, 2023.
Haveri City, Guttal And Rattihalli : The scope of work includes construction of RCC intake well, 4.5 mld water treatment plant (WTP) distribution network including SCADA automation and O&M of five years at an estimated cost of Rs 1,498.78 million. The last date for bid submission is December 5, 2023.
Yaragatti, Ramdurga, Boragoan, Kabbur, Kagwad-shedbal-ugarkhurd, Naganoor- Kalloli – Mallapur Pg Ghatprabha – Arambhavi – Mudalgi, Sindagi, Gajendragad and Kumta: The scope of work includes construction of RCC intake well and other allied infrastructure including SCADA automation and ]O&M of five years at an estimated cost of Rs 3,110.38 million. The last date for bid submission is November 22, 2023.
Alamela, Nalatwad, Chadchan, Talikote Muddebihal, Sankeshwar, Khanapur, Ainapur, Kudachi, Munavalli And Ankalagi-akkatangerhal Towns: The scope of project includes construction of 4.54 mld WTP, pump house, jack well, 44.33 km distribution network and 4800 household connections including SCADA automation and O&M of five years at an estimated cost of Rs 2,077.33 million. The last date for bid submission is November 22, 2023.

End Date: November 22, 2023; December 5, 2023

Download PDF

Download PDF

Download PDF

Download PDF


Implementing Agency: Nashik Municipal Corporation

Segment: Water Supply

Work: The scope of work includes the construction of an elevated reinforced cement concrete (RCC) break pressure tank (BPT) having a capacity of 20,00,000 litres, a raw water transmission line from BPT to Bara Bungalow parallel to the existing raw water transmission main, replacement of old raw water PSC line from Gangapur Dam to Bara Bungalow WTP by MS pipeline and other allied infrastructure.

End Date: December 20, 2023

Download PDF


Implementing Agency: Vadodara Municipal Corporation

Segment: Wastewater

Work: The scope of project includes engineering, procuring, providing, constructing, installing and commissioning (EPC) of 50 million litres per day (mld) STP and pumping station including a trial run of three months and Operation and Maintenance (O&M) for ten years.

End Date: December 2, 2023

Download PDF


Implementing Agency: Gujarat Water Supply and Sewerage Board (GWSSB)

Segment: Water Supply

Work: Abdasa: The scope of work includes providing, supplying, lowering, laying, jointing and commissioning of pipeline, construction of underground sump, elevated service reservoir (ESR), reinforced cement concrete (RCC) pump house, mechanical work, and related infrastructure including Operation and Maintenance (O&M) of 10 years at Abdasa in Kachch district. The work is likely to be completed in 18 months at an estimated cost of Rs 970 million.

Bhiloda, Himmatnagar, Vijaynagar and Idar: The scope of work includes working survey, soil investigation, design, build and operate (DBO) contract basis for providing, supplying, lowering, laying, jointing, testing and commissioning of pipeline network, pumping main and gravity main, providing, supplying and erecting pumping machinery at headwork and sub headwork, designing and construction of intake structure and related infrastructure at Bhiloda, Himmatnagar, Vijaynagar and Idar taluka in Aravalli and Sabarkantha districts including Operation and Maintenance (O&M) of ten years. The work is likely to be completed in 24 months at an estimated cost of Rs 902.95 million.

End Date: December 7, 2023

Download PDF

Download PDF


Implementing Agency: Vijayawada Municipal Corporation

Segment: Water Supply

Work: The scope of work includes construction of intake well, 45 million litres per day (mld) water treatment plant (WTP), pipelines, pump sets, and elevated level storage reservoir (ELSR), ground level storage reservoir (ELSR) including Operation and Maintenance (O&M) for five years along with defect liability period of two years in circle-III area of Vijayawada.

End Date: November 20, 2023

Download PDF


Implementing Agency: Faridabad Metropolitan Development Authority (FMDA)

Segment: Water Supply

Work: The scope of work includes design, construction, erection and commissioning of 5 ranney wells (radial collector wells of 10 million litres per day (mld) capacity each), 1 main booster station including purchase of land in revenue estate of village Basantpur and surrounding areas along the Yamuna flood plains in Faridabad district followed by three months trial run and Operation and Maintenance(O&M) for five years with defect liability period (DLP).

End Date: December 27, 2023

Download PDF


Implementing Agency: Tamil Nadu Water Supply and Drainage Board (TWAD)

Segment: Wastewater

Work: The scope of work includes development of collection system including house service connection, machine holes, pumping stations, pumping mains, lift stations and related infrastructure including trial run for six months and Operation and Maintenance (O&M) for five years.

End Date: December 13, 2023

Download PDF


Implementing Agency: Sundargarh Municipal Corporation

Segment: Wastewater

Work: The scope of work includes preparation of a comprehensive drainage master plan along with DPR for storm water drainage system and network including secondary, tertiary and street drains around the municipal area.

End Date: November 20, 2023

Download PDF


Implementing Agency: Assam Urban Water Supply and Sewarage Board

Segment: Water Supply

Work: The scope of work includes construction of reinforced cement concrete (RCC) overhead tanks, investigation and testing for foundation, design and drawing of the structure, construction of approved design, providing and fixing of pipes, valves and related infrastructure including testing and Operation and Maintenance (O&M) for five years.

End Date: November 21, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of project survey, soil investigation, design, supply of all materials, T&P required for completion of 24×7 water supply scheme (WSS) in selected wards of 7 towns in the state on turnkey basis.

End Date: November 23, 2023

Download PDF


Implementing Agency: Public Health And Municipal Engineering Department, Andhra Pradesh

Segment: Water Supply

Work: The scope of work includes surveying, investigation, designing, obtaining approvals from competent authority for designs and detailed drawings, bill of quantities (BOQs) for augmentation of water supply to Kurnool Municipal Corporation with Handri-Neeva Sujala Sravanthi (HNSS) canal as source and to Kadapa Municipal Corporation with Sri Pothuluri Veerabrahmendraswamy Balancing Reservoir (SPVBR) as source including five years of Operation and Maintenance (O&M) under the engineering, procurement and construction (EPC) mode.

End Date: November 16, 2023

Download PDF

Download PDF


Implementing Agency: Kakinada Municipal Corporation

Segment: Water Supply; Wastewater

Work: The scope of work includes preparation of detailed project report (DPR) for water supply and sewerage projects in Kakinada, Andhra Pradesh

End Date: November 6, 2023

Download PDF

Download PDF


Implementing Agency: Public Health And Municipal Engineering Department, Andhra Pradesh

Segment: Wastewater

Work: The scope of work includes investigation, survey, design and execution of UGD network in Zone I-IV of Narsapuram Municipality including the construction of sewers, manholes and lifting stations., construction of sewage treatment plant (STP) including mechanical and electrification works and Operation and Maintenance (O&M ) for three years including defect liability period of two years.

End Date: November 15, 2023

Download PDF


Implementing Agency: Uttarakhand Urban Sector Development Agency (UUSDA)

Segment: Water Supply

Work: The scope of project includes construction of 14 tubewells, rising main, 5 overhead tanks (OHTs) distribution network of 317.3 km and other related infrastructure including Operation and Maintenance (O&M) of 18 years.

End Date: November 30, 2023

Downlod PDF


Implementing Agency: Karnataka Urban Water Supply and Drainage Board

Segment: Water Supply

Work: The scope of work includes:
Chickmagaluru: Improvement of WSS in Tarikere, Kadur, Birur and Mudigere towns of Chickmagaluru districts including Operation and Maintenance (O&M) for five years at an estimated cost of Rs 994.95 million. The work will be completed in 18 months.

Mandya, Chamrajanagar and Mysuru: Improvement of WSS in Bellur towns of Mandya district, Hanur and Yelandur town of Chamrajanagar and K. R. Nagar and H. D. Kote tones of Mysuru district including Operation and Maintenance (O&M) for five years at an estimated cost of Rs 901.76 million. The work will be completed in 24 months.

End Date: Chickmagaluru (November 23, 2023); Mandya, Chamrajanagar and Mysuru (December 15, 2023)

Download PDF

Download PDF


Implementing Agency: Bihar Urban Infrastructure Development Corporation Limited (BUIDCO)

Segment: Wastewater

Work: The scope of project includes development of stormwater drainage (SWD) projects in Sitamarhi, Purnia, Bettiah, Chhapra, Bodhgaya, Sheoha and Jehanabad in Bihar.

End Date: November 11, 2023

Download PDF


Implementing Agency: Pudukkottai Municipal Corporation

Segment: Wastewater

Work: The scope of work includes the construction of UGSS in newly added and leftover areas of Pudukottai municipality including Operation and Maintenance (O&M) for five years.

End Date: November 10, 2023

Download PDF


Implementing Agency: Kancheepuram Municipal Corporation

Segment: Wastewater

Work: The scope of work includes the construction of UGSS in uncovered areas of Kancheepuram city in Tamil Nadu including Operation and Maintenance (O&M) for five years.

End Date: December 12, 2023

Download PDF


Implementing Agency: Dindigul City Municipal Corporation

Segment: Wastewater

Work: The scope of work includes the construction of UGSS in leftover areas of Dindigul city in Tamil Nadu including Operation and Maintenance (O&M) for five years.

End Date: December 12, 2023

Download PDF


Implementing Agency: Sahibzada Ajit Singh (S.A.S) Nagar Municipal Corporation

Segment: Wastewater

Work: The scope of the project includes preparation of area survey plan and DPR for proper disposal of SWD in low lying areas of the municipal corporation.

End Date: November 18, 2023

Download PDF


Implementing Agency: Guwahati Metropolitan Drinking Water and Sewerage Board

Segment: Water Supply

Work: The scope of work includes providing consultancy services for balance works under the South Guwahati West Water Supply Project

End Date: November 13, 2023

Download PDF


Implementing Agency: Uttarakhand Jal Sansthan

Segment: Water Supply

Work: The scope of work includes design, construction, supplying, laying, jointing, testing of gravity, rising distribution main, clear water reservoir, tubewell, house service connection and supervisory control and data acquisition (SCADA) automation including Operation and Maintenance (O&M) of five years.

End Date: November 10, 2023

Download PDF


Implementing Agency: Public Health And Municipal Engineering Department, Andhra Pradesh

Segment: Wastewater

Work: The scope of work includes sewage and septage management with construction of 35 million litres per day (mld) STP, investigation, survey, design, construction of diversion structures, conveyance system for abatement of sewage discharge in Tungabhadra River and STPs with Operation and Maintenance (O&M) for five years including defect liability period (DLP) of two years in Kurnool Municipal Corporation (KMC).

End Date: November 3, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN

Segment: Wastewater

Work: The scope of work includes survey, investigation, design, build, operate and transfer of interception, diversion and treatment works including drain tapping, interceptor trunk sewer of 2.17 km, rising mains length of 5.5 km., 6 million litre per day (mld) STP, feacal sludge treatment facility of 10 kilo litre per day (kld) with allied works. The project is likely to be completed in 18 months with three months of trial operations at an estimated cost of Rs 0.52 billion.

End Date: November 16, 2023

Download PDF


Implementing Agency: Assam Urban Infrastructure Investment Program (AUIIP)

Segment: Water Supply

Work: The scope of work includes topographical survey, geo-technical survey and necessary investigations for preparation of a comprehensive DPR for the projects.

End Date: October 31, 2023

Download PDF

Download PDF


Implementing Agency: Dharmapuri Municipal Corporation

Segment: Wastewater

Work: The scope of work includes construction of collection system including house service connections, pumping stations, pumping mains and lift stations and Operation and Maintenance (O&M) for five years.

End Date: November 30, 2023

Download PDF 


Implementing Agency: Chhindwara Municipal Corporation

Segment: Water Supply

Work: The scope of the project includes survey, soil investigation, design and construction of raw water gravity main, clear water pumping main having a length of 15.46 km, water treatment plant (WTP), overhead reservoirs, distribution network of 241.65 km, supervisory control and data acquisition (SCADA) automation.

End Date: November 22, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of work includes construction of three overhead tanks (OHTs), supply, laying and jointing of 109.84 km of distribution network. eight pump houses, 12,360 house connections and related infrastructure including three months of trial and run followed by Operation and Maintenance (O&M) for two years.

End Date: November 6, 2023

Download PDF


Implementing Agency: Mahadula Municipal Corporation

Segment: Wastewater

Work: The scope of work includes preparation of DPR, project development and management support for Mahadula water supply and underground sewerage scheme.

End Date: October 21, 2023

Download PDF 


Implementing Agency: Theni-Allinagaram Municipal Corporation

Segment: Wastewater

Work: The scope of work includes construction and Operation and Maintenance (O&M) of UGSS in Theni-Allinagaram  for five years at an estimated cost of Rs 610 million.

End Date: December 21, 2023

Download PDF


Implementing Agency: Mouda Nagar Panchayat

Segment: Wastewater

Work: The scope of work includes preparation of detailed project report, project development and management support.

End Date: October 20, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of the project includes survey, soil investigation, design, supply of all materials, labour, required for construction, erection, completion, testing and commissioning of water supply works such as reinforced cement concrete (RCC) overhead tanks (OHTs), concrete water recycling (CWR) cum pumping station, rising main, feeder main, distribution system, SCADA Room, chlorination room, meter room, panel room and other appurtenant works including supervisory control and data acquisition (SCADA) automation followed by trial run of 3 months and defect liability period of 12 months for civil works and 24 months for electric and mechanical works after completion of successful trial run.

End Date: November 9, 2023

Download PDF


Implementing Agency: Jabalpur Municipal Corporation

Segment: Wastewater

Work: The scope of project includes providing services for preparation of the present status of treatment and DPR for interception, diversion and treatment of sewage flowing in drains meeting river Narmada near Jabalpur Town of Madhya Pradesh.

End Date: October 26, 2023

Download PDF


Implementing Agency: Nagpur Metropolitan Region Development Authority (NMRDA)

Segment: Wastewater

Work: The scope of work includes developmnent of sewerage collection system, designing and construction of wet well, pumping station and sewerage treatment plant (STP) with supervisory control and data acquisition (SCADA) automation including Operation and Maintenance (O&M) of five years.

End Date: November 15, 2023

Download PDF

Download PDF

Download PDF

Download PDF


Implementing Agency: Rajamahendravaram Municipal Corporation

Segment: Wastewater

Work: The scope of work includes investigation, survey, design, supply, construction, installation, testing and commissioning of STP having capacity of 50.6 million litres per day (mld) on open technology sequential batch reactor (SBR) with three months trial run Post completion and Operation and Maintenance (O&M) of fiver years including two years defect liability period.

End Date: November 3, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of the project includes survey, soil investigation, design, supply of all materials, labour, required for construction, erection, completion, testing and commissioning of water supply works such as reinforced cement concrete (RCC) overhead tanks (OHTs), concrete water recycling (CWR) cum pumping station, rising main, feeder main, distribution system, SCADA Room, chlorination room, meter room, panel room and other appurtenant works including supervisory control and data acquisition (SCADA) automation followed by trial run of 3 months and defect liability period of 12 months for civil works and 24 months for electric and mechanical works after completion of successful trial run.

End Date: November 9, 2023

Download PDF


Implementing Agency: Bhopal Municipal Corporation

Segment: Water Supply

Work: The scope of work includes survey, soil investigation, design and execution of various works for augmentation of water supply system including construction of an intake well raw water pump house installation of waw/clear water pumps, substation including 33KVH feeder, water treatment plant (WTP), providing, laying, jointing, testing and commissioning of raw/clear water pumping/feeder main and distribution network including excavation, refilling, road cutting /dismantling, restoration to its original condition, providing and fixing required valves (Sluice, Air, Scour, PRV etc.) specials, fittings, flow meters. Construction of valve chambers, thrust blocks and house service connections/ bulk connection and supervisory control and data acquisition (SCADA) automation.

End Date: October 20, 2023

Download PDF


Implementing Agency: Jabalpur Municipal Corporation

Segment: Water Supply

Work: The scope of work includes construction of intake well cum pump house having capacity of 135 million litres per day (mld), installation and commissioning of raw water pumps, control panels, laying of raw water MS pumping main, construction of a 54 mld water treatment plant (WTP), clear water pump house, raw water pipeline network of 20.751 km, clear water pipeline network of 40,445 km, sump well, 33kv single circuit HT feeder line, repair work of existing WTP at Lalpur, Bhongadwar and Ranjhi along with SCADA automation and all other related infrastructure.

End Date: November 8, 2023

Download PDF


Implementing Agency: Vidisha Municipal Corporation

Segment: Water Supply

Work: The scope of work includes survey, soil investigation, design and construction of intake well at Halali dam, water pump house, approach bridge, providing, laying, jointing, testing and commissioning of raw water pumping main from Halali dam to existing water treatment plant (WTP), construction of 11 million litres per day (mld) WTP and retrofitting of existing 9 mld WTP, feeder main pipe of 9.971 km and distribution network of 63.132 km and related infrastructure.

End Date: November 24, 2023

Download PDF


Implementing Agency: Pune Metropolitan Region Development Authority (PMRDA)

Segment: Water Supply; Wastewater

Work: The scope of work includes the preparation of a detailed project report (DPR) for external water supply, external sewerage system, water treatment plant (WTP), raw water rising main and sewage treatment plant (STP) including post tender activity for sanctioned cost town planning scheme.

End Date: October 16, 2023

Download PDF

Download PDF

Download PDF


Implementing Agency: Pudukkottai Municipal Corporation

Segment: Wastewater

Work: The scope of work includes the construction of UGSS in newly added and leftover areas of Pudukottai municipality including Operation and Maintenance (O&M) for five years.

End Date: October 26, 2023

Download PDF


Implementing Agency: Avadi City Municipal Corporation

Segment: Wastewater

Work: The scope of work includes the construction of UGSS in leftover areas of Pudukottai municipality in Tamil Nadu including Operation and Maintenance (O&M) for five years.

End Date: November 29, 2023

Download PDF


Implementing Agency: Uttarakhand Urban Sector Development Agency (UUSDA)

Segment: Water Supply

Work: The scope of work includes development of tubewells, rising main, overhead tank (OHTs), a distribution network of 119 km, sewerage treatment plant (STP) having capacity of 7 millon litres per day (mld), SCADA automation and allied infrastructure with O&M of 18 years.

End Date: October 18, 202

Download PDF


Implementing Agency: Public Health And Municipal Engineering Department, Telangana

Segment: Water Supply

Work: Package 1: It includes water supply projects in 30 ULBs and sewerage projects in 3 ULBs of Adilabad, Karimnagar and Warangal divisions at an estimated cost of Rs 11,105.56 million.
Package 2: It includes water supply projects in 26 ULBs and sewerage projects in 4 ULBs of Nalgonda and Khamman divisions at an estimated cost of Rs 1,135.32 million.
Package 3: It includes water supply projects in 42 ULBs and sewerage projects in 2 ULBs of Nizamabad and Mahabubnagar divisions at an estimated cost of Rs 1,270.59 million.

End Date: November 16, 2023

Download PDF

Download PDF

Download PDF


Implementing Agency: Jharkhand Urban Infrastructure Development Corporation Limited (JUIDCO)

Segment: Water Supply

Work: The scope of work includes GIS-based mapping, surveys, soil testing, design, supply, construction and commissioning of intake jack well, approach bridge, centrifugal pump, 11 million litres per day (mld) water treatment plant (WTP), 9.173 km of raw water transmission main, 6.277 km of treated water transmission main, distribution network of 79.868 km and supervisory control and data acquisition (SCADA) automation and related infrastructure including Operation and Maintenance (O&M) of five years.

End Date: October 27, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Wastewater

Work: The scope of work involves survey, soil investigations, design, supply of materials and labour, construction, erection, testing and commissioning of 20 million litres per day (mld) sewage treatment plant (STP) including co-treatment plant, rising main, manholes, pumping station, cleaning gap connections and repairing of existing damaged structure followed by a three-month defect liability period (DLP).

End Date: October 27, 2023

Download PDF


Implementing Agency: NICDIT Krishnapatnam Industrial City Development Limited (NKICDL)

Segment: Wastewater

Work: The scope of work includes development of potable water supply, network development, recycle water supply network, stormwater drainage, residential sewerage network, industrial effluent collection network, pumping station, rising main, water treatment plant (WTP), sewage treatment plant (STP), common effluent treatment plant (CETP) including Operation and Maintenance (O&M) of four years.

End Date: November 9, 2023

Download PDF


Implementing Agency: Rajasthan Urban Drinking Water Sewerage and Infrastructure Corporation Limited (RUDSICO)

Segment: Wastewater

Work: The scope of work includes providing, laying, jointing, testing and commissioning of sewerage system and all ancillary works along with design, construction, supply, installation, testing and commissioning of civil, mechanical, electrical, instrumentation and other necessary works of 1 mld sewage pumping station(SPS), 3 mld STP based on sequential batch reactor (SBR) process with provision for treated wastewater reuse including one year of defect liability and 10 years of Operation and Maintenance (O&M).

End Date: December 4, 2023

Download PDF


Implementing Agency: Tiruvannamalai Municipal Corporation

Segment: Wastewater

Work: The scope of work includes construction and Operation and Maintenance (O&M) for five years of UGSS to added areas/leftout areas in Thiruvannamalai municipality.

End Date: December 22, 2023

Download PDF


Implementing Agency: Bidasar Nagar Palika

Segment: Water Supply, Wastewater

Work: The scope of project includes preparation of DPR for comprehensive sewerage project, water supply project, drainage projects, reuse of treated water and any other related work.

End Date: October 2, 2023

Download PDF


Implementing Agency: Kadapa Municipal Corporation

Segment: Wastewater

Work: The scope of work includes the development of major storm water drainage (SWD) system phase I in Kadapa, Andhra Pradesh.

End Date: October 9, 2023

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water Supply

Work: The scope of work includes design and construction of ground storage level reservoirs, high lift pump house, chlorine room, store room, sub station building, zonal over head reservoir and allied infrastructure including soil investigation of different capacity along with rising main, laying of distribution pipeline, 51,946 functional house tap connections (FHTCs) etc. including Operation and Maintenance (O&M) for five years after successful trial of 180 days.

End Date: October 31, 2023

Download PDF


Implementing Agency: Chandigarh Municipal Corporation (CMC)

Segment: Wastewater

Work: The scope of the project includes strengthening of T.T. WSS and laying of T.T. water lines in left out areas to supply tertiary treated water in Chandigarh under the Atal Mission for Rejuvenation and Urban Transformation (AMRUT) 2.0.

End Date: October 4, 2023

Download PDF


Implementing Agency: Guwahati Metropolitan Drinking Water and Sewerage Board (GMDW&SB)

Segment: Wastewater

Work: The scope of project involves design and construction of sewerage treatment plants, pumping and lifting stations, lateral sewers including connections to collection chambers, faecal sludge and septage management facilities under Guwahati Sewerage Project (Zone 1).

End Date: November 1, 2023

Download PDF


Implementing Agency: Nagpur Metropolitan Region Development Authority (NMRDA)

Segment: Wastewater

Work: The scope of work includes development of sewerage collection system, designing, construction of wet well, pumping station and sewerage treatment plant (STP) with supervisory control and data acquisition (SCADA) automation and Operation and Maintenance (O&M) for five years.

End Date: October 9, 2023

Download PDF


Implementing Agency: Water Resource Zone, Udaipur

Segment: Water Supply

Work: The scope of work includes planning, design and construction of Zawar Anicut with feeder channel and tunnel for diversion of water to Daya Dam Tehsil in Sarada, Udaipur district on engineering, procurement and construction (EPC) single responsibility turn-key basis, including Operation and Maintenance (O&M) of 8 years.

End Date: September 28, 2023

Download PDF


Implementing Agency: Sahibzada Ajit Singh (S.A.S) Nagar Municipal Corporation

Segment: Wastewater

Work: The scope of the project includes preparation of area survey plan and DPR for proper disposal of SWD in low lying areas of the municipal corporation.

End Date: October 7, 2023

Download PDF


Implementing Agency: Jharkhand Urban Infrastructure Development Company Limited (JUIDCo)

Segment: Water Supply

Work: The scope of work includes:
Medininagar: Construction and five years of Operation and Maintenance (O&M) of water supply system. It involves intake works, rising main, 17 mld water treatment plant (WTP), clear water main, elevated service reservoirs (ESR), distribution network and house service connections (HSCs).
Jhumri Telaiya: Construction and five years of O&M of water supply system. It involves intake works, rising main, 35.5 mld WTP, clear water main, ESRs, distribution network and HSCs.

End Date: October 26, 2023

Download PDF

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water Supply

Work: The scope of work includes design and construction of ground storage level reservoirs, high lift pump house, chlorine room, store room, sub station building, zonal over head reservoir and allied infrastructure including soil investigation of different capacity along with rising main, laying of distribution pipeline, 51,946 functional house tap connections (FHTCs) etc. including Operation and Maintenance (O&M) for five years after successful trial of 180 days.

End Date: September 12, 2023

Download PDF


Implementing Agency: Tambaram City Municipal Corporation

Segment: Water Supply

Work: The scope of work includes preparation and submission of DPR , preliminary drawings, designs specification, preliminary cost estimates and obtaining necessary approvals.

End Date: September 20, 2023

Download PDF


Implementing Agency: Tamil Nadu Water Supply and Drainage Board

Segment: Wastewater

Work: The scope of work includes development of UGSS in added areas of Vellakinar, Chinnavedampatty and Saravanampatty covering beards 26 to 29  and in parts in wards 42(1) and 43 including Operation and Maintenance (O&M) for five years.

End Date: October 25, 2023

Download PDF


Implementing Agency: Public Health And Municipal Engineering Department, Andhra Pradesh

Segment: Wastewater

Work: The scope of work includes investigation, survey, design and execution of UGD network in Zone I-IV of Narsapuram Municipality including construction of sewers, manholes and lifting stations., construction of sewage treatment plant (STP) including mechanical and electrification works and Operation and Maintenance (O&M ) for three years including defect liability period of two years.

End Date: September 27, 2023

Download PDF


Implementing Agency: Kadapa Municipal Corporation

Segment: Wastewater

Work: The scope of the project includes development of major storm water drainage (SWD) system phase I in Kadapa, Andhra Pradesh.

End Date: September 21, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (Urban)

Segment: Water Supply

Work: The scope of work includes survey, design, soil investigation, supply of all materials, construction of overhead tanks (OHTs), pump house, laying and joining of rising main, distribution pipeline, house service connections, repair of existing OHTs, tube well, PLC supervisory control and data acquisition (SCADA) automation.

End Date: September 13, 2023

Download PDF


Implementing Agency: Rajamahendravaram Municipal Corporation

Segment: Water Supply

Work: The scope of work includes finding the gap in drinking water supply in the proposed work area, analyzing the quantum of drinking water supply required for the proposed works areas in the urban local body (ULB) and finalization of a feasible source of water, preparing detailed project report (DPR), estimates, drawings and appraisal of the project of providing drinking water supply facilities for areas in consultation with the ULB.

End Date: September 19, 2023

Download PDF


Implementing Agency: Chhindwara Municipal Corporation

Segment: Water Supply

Work: The scope of the project includes survey, soil investigation, design and construction of raw water gravity main, clear water pumping main having a length of 15.46 km, water treatment plant (WTP), overhead reservoirs, distribution network of 241.65 km supervisory control and data acquisition (SCADA) automation.

End Date: September 22, 2023

Download PDF


Implementing Agency: Jharkhand Urban Infrastructure Development Corporation Limited (JUIDCO)

Segment: Water Supply

Work: The scope of work includes GIS-based mapping, surveys, soil testing, design, supply, construction and commissioning of intake jack well, approach bridge, centrifugal pump, 11 million litres per day (mld) water treatment plant (WTP), 9.173 km of raw water transmission main, 6.277 km of treated water transmission main, distribution network of 79.868 km and supervisory control and data acquisition (SCADA) automation and related infrastructure including Operation and Maintenance (O&M) of five years.

End Date: September 25, 2023

Download PDF


Implementing Agency: Water Supply and Sanitation Department, Maharashtra

Segment: Wastewater

Work: The scope of work includes hydraulic and structural designs, construction of faecal WTP including Operation and Maintenance (O&M) of the plant for one year,

End Date: October 11, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of work includes construction of overhead tank (OHT), pump house, clear water reservoir (CWR), repair of existing OHT, laying and jointing of rising main, distribution system, tube-wells, programmable logic controller (PLC) supervisory control and data acquisition (SCADA) automation, commissioning, testing, trial and run, defect liability and related infrastructure.

End Date: September 11, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of work includes survey, soil investigation, design, supply of material and labour, construction of overhead tank (OHT), pump house, repair of existing OHT, laying and jointing of rising main, distribution system, tube-wells, programmable logic controller (PLC) supervisory control and data acquisition (SCADA) automation, commissioning, trial and run, defect liablity and related infrastructure for Tanda WSS and house connections.

End Date: August 29, 2023

Download PDF


Implementing Agency: Bihar Urban Infrastructure Development Corporation Limited (BUIDCO)

Segment: Wastewater

Work: The scope of the project includes the development of stormwater drainage (SWD) for Darbhanga town areas in Bihar under Nischay -2 Scheme.

End Date: September 1, 2023

Download PDF


Implementing Agency: Shegaon Municipal Council

Segment: Water Supply

Work: The scope of work includes construction of raw water gravity main, water treatment plant (WTP) of 7.5 million litres per day (mld), interconnection of existing and proposed pure water sump of WTP, pure water gravity main, reinforced cement concrete (RCC) elevated service reservoir (ESR) of 710000 litres, distribution network of 168 km and related infrastructure with supervisory control and data acquisition (SCADA) automation.

End Date: September 11, 2023

Download PDF


Implementing Agency: Tiruchirappalli City Corporation

Segment: Wastewater

Work: The scope of work includes design, build and commissioning of a 100 million litres per day (mld) sewage treatment plant (STP) at Panjappur using sequencing bioreactor (SBR) technology with 10 mld TTUF including Operation and Maintenance (O&M) of 15 years at Panjapur, Tiruchirapalli.

End Date: November 22, 2023

Download PDF


Implementing Agency: Sahibzada Ajit Singh (S.A.S) Nagar Municipal Corporation

Segment: Wastewater

Work: The scope of the project includes preparation of area survey plan and DPR for proper disposal of SWD in low lying areas of the municipal corporation.

End Date: September 5, 2023

Download PDF


Implementing Agency: Ratlam Nagar Palika

Segment: Water Supply

Work: The scope of the project includes providing, laying, and jointing of water pipeline of any material or nature like rising, feeder or distribution, construction of 12 million litre per day (mld) water treatment plant (WTP) and construction of intake well/pump house, an overhead tank of ground-level service reservoir.

End Date: September 14, 2023

Download PDF


Implementing Agency: Public Health And Municipal Engineering Department, Andhra Pradesh

Segment: Wastewater

Work: The scope of work includes sewage and septage management with construction of 35 million litres per day (mld) STP, investigation, survey, design, construction of diversion structures, conveyance system for abatement of sewage discharge in Tungabhadra River and STPs with Operation and Maintenance (O&M) for five years including defect liability period (DLP) of two years in Kurnool Municipal Corporation (KMC).

End Date: September 5, 2023

Download PDF


Implementing Agency: Bihar Urban Infrastructure Development Corporation Limited (BUIDCO)

Segment: Wastewater

Work: The scope of work includes design and construction of two STPs having capacity of 7 million litres per day (mld) and 6 mld along with all appurtenant structures and allied works, disinfection controlled with supervisory control and data acquisition (SCADA) automation including survey, review the designs, redesign where necessary, construction of one pumping station with 5998 mtr interception drain, including screens and mechanically operated gates facilitating including effluent channel disposal of treated effluent through pipeline of 302 mtr with Operation and Maintenance (O&M) of 15 years.

End Date: August 28, 2023

Download PDF


Implementing Agency: Vidisha Municipal Corporation

Segment: Water Supply

Work: The scope of work includes survey, soil investigation, design and construction of intake well at Halali dam, water pump house, approach bridge, providing, laying, jointing, testing and commissioning of raw water pumping main from Halali dam to existing water treatment plant (WTP), construction of 11 million litres per day (mld) WTP and retrofitting of existing 9 mld WTP, feeder main pipe of 9.971 km and distribution network of 63.132 km and related infrastructure.

End Date: September 12, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Wastewater

Work: The scope of work includes survey, investigation, design, supply, laying, commissioning and testing of sewer pipe in lateral/branch sewers and balance house connection & road reinstatement & its appurtenant works in sewerage District 3 Part 2 of Lucknow city.

End Date: August 23, 2023

Download PDF


Implementing Agency: Vasai Virar City Municipal Corporation (VVMC)

Segment: Wastewater

Work: The scope of work includes survey, designing, providing, laying, lowering and commissioning of sewer network including property service connection and road restoration works.

End Date: September 21, 2023

Download PDF


Implementing Agency: Gujarat water supply and sewerage board (GWSSB)

Segment: Water Supply

Work: The scope of work includes water supply works in six districts:

Sayla and Chotila : The scope of work involves providing, supplying, laying, testing commissioning of reinforced cement concrete (RCC) underground sump, pump house D.I./PVC pipeline, pumping machinery and additional storage for remodelling of distribution network of Surendarnagar integrated (phase -II) part- B Group -1 Regional Water Supply Scheme of Surendranagar district based on Dholi Dhaja Dam including Operation and Maintenance (O&M) of new and existing works for supply of water for 120 months at an estimated cost of the project is Rs 727.4 million.
Dhrangadhra, Dasada, Halvad and Lakhtar: The scope of work includes providing, supplying, laying testing commissioning of water treatment plant (WTP), RCC underground sump, RCC elevated service reservoir (ESR), pump house D.I./PVC Pipeline and pumping machinery and additional storage for remodelling of distribution network of NCD-4 (GROUP 8) regional Water Supply Scheme based on Maliya branch Canal at Malvan offtake and NC-30 for Distribution Network of Dhrangadhra, Dasada, Halvad & Lakhtar Taluka including O&M of new and existing works for supply of water for 120 months at an estimated cost of Rs 848.36 million.

End Date: August 21, 2023

Download PDF

Download PDF


Implementing Agency: Water Supply and Sanitation Department, Maharashtra

Segment: Wastewater

Work: The scope of work includes empanelment of contractors for construction of  grey water treatment plants (WTP) in villages having population of more than 5000 in Maharashtra under the Swachh Bharat Mission (Grameen) Phase-II.

End Date: September 20, 2023

Download PDF

Download PDF


Implementing Agency: Gujarat Water Supply and Sewerage Board (GWSSB)

Segment: Water Supply

Work: The scope of work includes providing, supplying, lowering, laying, jointing of pipeline, constructing water treatment plant (WTP), reinforced cement concrete (RCC) elevated service reservoir (ESR)/ underground sumps, pump house and connecting line to various village and other related infrastructure including Operation and Maintenance (O&M) for 10 years.

End Date: September 24, 2023

Download PDF


Implementing Agency: Rajasthan Urban Drinking Water Sewerage and Infrastructure Corporation Limited (RUDSICO)

Segment: Wastewater

Work: The scope of work includes:Jaisinghpura Khor: The scope of work includes upgradation of 50 million litres per day (mld) sewage treatment plant (STP) and construction of 30 mld STP and reuse of treated effluent from the STPs at Jaisinghpura Khor, Jaipur including design, construction, supply, installation, testing and commissioning of civil, mechanical, electrical, instrumentation, supervisory control and data acquisition (SCADA), Online Continuous Emission Monitoring System (OCEMS) and other necessary works including 1 year defect liability with 15 years Operation and Maintenance (O&M) on hybrid annuity model ( HAM) contract basis at an estimated cost of Rs 2,030.7 million.

Jaipur Heritage I: The scope of work includes construction of 30 mld STP to treat sewage and reuse of treated effluent from the STPs at ward 99 and 100, Jaipur Heritage including design, construction, supply, installation, testing and commissioning of civil, mechanical, electrical, instrumentation, SCADA and OCEMS and other necessary works including 1 year defect liability with 15 years O&M on HAM contract basis at an estimated cost of Rs 840.74 million.

Bhinmal: The scope of work includes providing, laying, jointing, testing and commissioning of sewerage system and all ancillary works along with design, construction, supply, installation, testing and commissioning of civil, mechanical, electrical, instrumentation and other necessary works of 1 mld sewage pumping station(SPS), 3 mld STP based on sequential batch reactor (SBR) process with provision for treated wastewater reuse including one year of defect liability and 10 years of O&M at an estimated cost of Rs 548.25 million.

End Date: September 4, 2023

Download PDF

Download PDF

Download PDF


Implementing Agency: Bhopal Municipal Corporation

Segment: Water Supply

Work: The scope of work includes survey, soil investigation, design and execution of various works for augmentation of water supply system including construction of an intake well raw water pump house installation of waw/clear water pumps, substation including 33KVH feeder, water treatment plant (WTP), providing, laying, jointing, testing and commissioning of raw/clear water pumping/feeder main and distribution network including excavation, refilling, road cutting /dismantling, restoration to its original condition, providing and fixing required valves (Sluice, Air, Scour, PRV etc.) specials, fittings, flow meters. Construction of valve chambers, thrust blocks and house service connections/ bulk connection and supervisory control and data acquisition (SCADA) automation.

End Date: September 8, 2023

Download PDF


Implementing Agency: Nagar Palika Nigam, Dewas

Segment: Water Supply

Work: The scope of work includes survey, soil investigation, design and construction of intake well, pump house, overhead tank, 30 million litre per day (mld) water treatment plant (WTP), house service connection, supervisory control and data acquisition system (SCADA) system and other related infrastructure.

End Date: August 25, 2023

Download PDF 


Implementing Agency: Madhya Pradesh Urban Development Company Limited (MPUDCL)

Segment: Wastewater

Work: The scope of work involves the balance works of survey, review the designs, redesign where necessary and build sewage collection and conveyance system, sewage treatment and disposal system of Sendhwa Nagar Palika, district Barwani in Madhya Pradesh and operation and maintenance (O&M) for 10 years.

End Date: September 15, 2023

Download PDF


Implementing Agency: Water Resource Department, Rajasthan

Segment: Water Supply

Work: The scope of work includes planning, design and construction of Zawar A nicut with feeder channel and tunnel for diversion of water to Daya Dam Tehsil in Sarada, Udaipur District on engineering, procurement and construction (EPC) single responsibility turn-key basis, including Operation and Maintenance (O&M) of 8 years.

End Date: August 10, 2023

Download PDF


Implementing Agency: Uttarakhand Urban Sector Development Agency (UUSDA)

Segment: Water Supply

Work: The scope of work includes water supply works in three towns:

Champawat: The scope of work includes construction of intake well, raw water rising main,  intermediate pumping station, clear water rising main, 3.5 million litres per day (mld) water treatment plant (WTP), distribution network, supervisory control and data acquisition (SCADA) automation and allied infrastructure with 18 years of Operation and Maintenance (O&M).

Vikas Nagar: The scope of work includes development of tubewells, rising main, overhead tank (OHTs), a distribution network of 119 km, sewerage treatment plant (STP) having capacity of 7 mld, SCADA automation and allied infrastructure with O&M of 18 years.

Kotdwar (Zone 2): It includes construction of tubewells, rising main, OHTs, distribution network of 299.616 km, supervisory control and data acquisition (SCADA) automation and allied infrastructure with 18 years of O&M.

End Date: September 23, 2023

Download PDF

Download PDF

Download PDF


Implementing Agency: Bhiwandi Nizampur City Municipal Corporation

Segment: Water Supply

Work: The scope of the project includes construction of jackwell, overhead pump house, retaining wall, sub station, reinforced cement concrete (RCC) bridges, raw water and pure water rising mains, two conventional water treatment plants (WTPs) having capacities of 123 million litre per day (mld) and 53 mld, RCC Sumps, RCC master balancing reservoir (MBR)/ elevated service reservoir (ESR)/ground service reservoir (GSR), DI leading mains and other miscellaneous work.

End Date: August 10, 2023

Download PDF


Implementing Agency: Salem City Municipal Corporation

Segment: Wastewater

Work: The scope of the project includes construction of underground sewerage system (UGSS) in uncovered areas of Salem, Tamil Nadu.

Package 1: It includes construction and Operation and Maintenance (O&M) for 5 years of UGSS in Zone I: ward no. 20, 21, 22 and 24 at an estimated cost of Rs 822.4 million.

Package 2: It includes construction and O&M for 5 years of UGSS in Zone I: ward no. 1, 2, 3, 23, 24 and 25, Zone II: ward no. 4, 5, Zone-III: ward no. 50, 51, 54, 57, 58, 59 at an estimated cost of Rs 977.8 million.

Package 3: It includes construction and O&M for 5 years of UGSS in  Zone -IV: ward no. 58, 59, 60 at an estimated cost of Rs 1,399.2 million.

Package 4: It includes construction and O&M for 5 years of UGSS in Zone -I: ward no.1, Zone -II: ward no. 6, 7, 8, 12, Zone -III: ward no. 9, 36, 37 and 38 at an estimated cost of Rs 1,497.9 million.

End Date: November 17, 2023

Download PDF

Download PDF

Download PDF

Download PDF


Implementing Agency: Uttarakhand Urban Sector Development Agency (UUSDA)

Segment: Water Supply

Work: Haldwani (Package 2): The scope of the work includes development of tube wells, rising main, overhead tanks (OHTs), water supply distribution network of 180 km, sewerage network of 7 km and sewerage treatment plant (STP) of 10.5 million litres per day (mld), supervisory control and data acquisition (SCADA) automation with Operation and Maintenance (O&M) of 18 years and allied infrastructure.

Tanakpur: The scope of the work includes development of tube wells, rising main, OHTs, water supply distribution network of 53.66 km, SCADA automation with O&M of 18 years.

End Date: September 23, 2023

Download PDF

Download PDF


Implementing Agency: Public Work Department, Delhi

Segment: Wastewater

Work: The scope of work includes the preparation of a detailed project report (DPR) within six months, one year of project execution, one year of solution validation and overall project supervision.

End Date: September 12, 2023

Download PDF

Download PDF


Implementing Agency: Nagpur Metropolitan Region Development Authority (NMRDA)

Segment: Water Supply; Wastewater

Work: The scope of work involves preparation of detailed project report (DPR) and project management consultancy (PMC) for water supply and sewerage projects to be undertaken in the NMRDA area in Maharshtra.

End Date: August 3, 2023

Download PDF


Implementing Agency: Chandigarh Municipal Corporation (CMC)

Segment: Water Supply

Work: The scope of the project includes strengthening of T.T. WSS and laying of T.T. water lines in left out areas to supply tertiary treated water in Chandigarh under the Atal Mission for Rejuvenation and Urban Transformation (AMRUT) 2.0.

End Date: August 1, 2023

Download PDF


Implementing Agency: Madhya Pradesh Industrial Development Corporation Limited

Segment: Water Supply

Work: The scope of the project includes survey, design, construction, testing and commissioning of WSS for PM Mitra Park with 10 years of Operation and Maintenance (O&M).

End Date: August 14, 2023

Download PDF


Implementing Agency: Municipal Corporation of Rewa

Segment: Water Supply

Work: The scope of the project includes survey, soil investigation, design and execution of various works for augmentation of water supply system including construction of an intake well, raw water pump house, installation of raw/ clear water pumps, substation including 33kv high tension (HT) feeder, water treatment plant, elevated service reservoir (ELSR) and ground-level storage reservoir (GLSR), providing, laying, jointing, testing and commissioning of raw/clear water pumping/feeder main and distribution network including excavation, refilling, road cutting /dismantling, restoration to its original condition, providing and fixing required valves (sluice, air, scour, pressure reducing valve (PRV) etc. specials, fittings, flowmeters. construction of valve chambers, thrust blocks and house service connections, automation supervisory control and data acquisition (SCADA).

End Date: July 31, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Wastewater

Work: The scope of work includes survey, investigation, design, supply, laying, commissioning and testing of sewer pipe in lateral/branch sewers and balance house connection & road reinstatement & its appurtenant works in sewerage district 3 Part 1 Phase 1 of Lucknow city.

End Date: August 1, 2023

Download PDF


Implementing Agency: Rajasthan Urban Drinking Water Sewerage and Infrastructure Corporation Limited (RUDSICO)

Segment: Wastewater

Work: The scope of work includes providing, laying, jointing, testing and commissioning of sewerage system and all ancillary works along with design, construction, supply, installation, testing and commissioning of civil, mechanical, electrical, instrumentation and other necessary works of sewerage network and construction of one sewerage treatment plant (STP), including 1 year defect liability with five years Operation and Maintenance (O&M).

End Date: August 24, 2023

Download PDF


Implementing Agency: Water Resources Zone, Udaipur

Segment: Water Supply

Work: The scope of the project includes:
Dams: Planning, design and construction of Dewas – 3 and 4 dams in Gogunda tehsil of Udaipur district on engineering procurement and construction (EPC) single responsibility turn-key basis including 10 years of Operation and Maintenance (O&M) at an estimated cost of Rs 3,799.1 million.
Tunnels: Planning, design and construction of tunnels from Dewas – 3 and 4 dams in Gogunda tehsil of Udaipur district on EPC single responsibility turn-key basis including 10 years of O&M at an estimated cost of Rs 4,415.7 million.

End Date: August 17, 2023

Download PDF


Implementing Agency: Department of Drinking Water and Sanitation, Uttarakhand

Segment: Wastewater

Work: The scope of work includes:
Haridwar (Package 2): Supplying, laying, jointing, constructing, testing and commissioning of sewerage networks, house service connections and sewage pump station in Haridwar (Zone D and Zone E) at an estimated cost of Rs 2,075.54 million.
Rishikesh (Package 6): Supplying, laying, jointing, constructing, testing and commissioning of sewerage networks, house service connections and sewage pump station in Rishikesh (Zone PSZ-1, Zone PSZ-2, Zone PSZ-3 and Zone GSZ-2) at an estimated cost of Rs 1,158.12 million.

End date: August 25, 2023

Download PDF

Download PDF


Implementing Agency: Ahmedabad Municipal Corporation (AMC)

Segment: Wastewater

Work: The scope of work is providing and Laying eastern trunkmain with pushing work in the Eastern Area starting from Kathwada to Vinzol sewage treatment plant (STP) on 36.0 mt. road and rising main from Odhav sewage pumping station (SPS) in the East Zone of AMC Area in Gujarat

Publish Date:  August 17, 2023

End Date: September 4, 2023

Download PDF


Implementing Agency: Indore Municipal Corporation

Segment: Wastewater

Work: The scope of work includes design, construction of STPs of installed capacity 120, 40 and 35 million litres per day (mld), survey, review of designs, new I&D of sewer network, survey, design, construction of three pumping station and appurtenant structures and allied works including Operation and Maintenance (O&M) of 15 years.

End Date: December 12, 2023

Download PDF


Implementing Agency: Irrigation Department, Uttarakhand

Segment: Wastewater

Work: The scope of work includes preparation of Geographic Information System (GIS) based master drainage plan and DPR for long-term measures.

End Date: July 22, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of work includes survey, soil investigation, design, supply of material and labour, construction of overhead tank (OHT), pump house, repair of existing  OHT, laying and jointing of rising main, distribution system, tube-wells, programmable logic controller (PLC) supervisory control and data acquisition (SCADA) automation, commissioning, trial and run, defect liablity  and related infrastructure for Tanda WSS and house connections.

End Date: July 31, 2023

Download PDF


Implementing Agency: Indore Municipal Corporation

Segment: Wastewater

Work: The scope of the project includes PMC services  for sewerage improvement works and construction of 35 million litres per day (mld) sewage treatment plant (STP).

End Date: November 22, 2023

Download PDF


Implementing Agency: Loha Municipal Council

Segment: Water Supply

Work: The scope of the project includes the construction of raw water rising main pipelines of gravity main, jack-well or intake well, elevated service reservoir (ESR), water treatment plant (WTP), pumping machinery, distribution system, supervisory control and data acquisition (SCADA) automation and pump as turbine (PaT) for micro hydro power generation unit.

End Date: July 28, 2023

Download PDF


Implementing Agency: Indore Municipal Corporation

Segment: Wastewater

Work: The scope of work includes PMC services for sewerage improvement works including construction and Operation and Maintenance (O&M) of sewage treatment plants (STPs) in Indore.

End Date:  July 11, 2023

Download PDF


Implementing Agency: Bihar Urban Infrastructure Development Corporation Limited (BUIDCo)

Segment: Wastewater

Work: The scope of the project includes construction, erection, supply, installation, testing and commissioning of two stormwater drainage pumping stations and the construction of about 34.72 km of drainage network in Patna Nagar Nigam, Khagaul, Danapur, Phulwarisharif and the Adjoining areas of Catchment-1 and Catchment-9.

End Date: August 22, 2023

Download PDF


Implementing Agency: Public Health and Municipal Engineering Department, Andhra Pradesh

Segment: Water Supply

Work: The scope of the project includes upgradation of water supply improvement scheme in Ongole Municipal Corporation with Ramatheertham balancing reservoir as source and performance based Operation and Maintenance (O&M) for five years including two years defect liability period (DLP).

End Date: July 12, 2023

Download PDF


Implemeting Agency: Municipal Corporation of Greater Mumbai (MCGM)

Segment : Wastewater

Work: The scope of work project management consultancy (PMC) bids for Malad wastewater treatment facility (WWTF) under the Mumbai Sewerage Disposal Project Stage II.

End Date: July 4, 2023

Download PDF


Implementing Agency: Navi Mumbai Municipal Corporation (NMMC)

Segment: Water Supply

Work: The scope of work includes design and construction of working survey, transmission main, reinforced cement concrete (RCC) ground storage reservoir (GSR) and sump, pump house, installation of pumping machinery, substation room, pure water rising main, dismantling of elevated storage reservoir (ESR) and GSR, repairs of ESR and GSR, construction of RCC ESR, distribution network system, road restoration, test and trial run.

End Date: July 3, 2023

Download PDF


Implementing Agency: Guntur Municipal Corporation

Segment: Water Supply

Work: The scope of work involves preparation of DPR for comprehensive water supply improvement scheme in Jagananna Housing Colonies at Navaratnaalu – Pedalandariki Illu (NPI) layouts-II and III of Budampadu area, NPI Layouts – I, II, III, IV and V of Etukuru area and NPI Layout of Pothuru area in Guntur Municipal Corporation.

End Date: June 26, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of the project includes the construction of the overhead tank, CWR, pump house, laying and jointing rising main, the distribution system and tube-wells including programmable logic controller (PLC) supervisory control and data acquisition (SCADA) automation. It will also involve commissioning, testing, trial and run, defect liabilities and handling the complete works on a turn-key basis. The project will likely be completed in 24 months at an estimated cost of Rs 933.01 million.

End Date: June 27, 2023

Download PDF


Implementing Agency : Uttar Pradesh Jal Nigam (UPJN)

Segment: Wastewater

Work : The scope of the project includes survey, soil investigation, supply, laying, jointing, testing and commissioning of sewer line by open cut and trenchless method as required with apparent works, construction of 68 million litre per day (mld) sewage treatment plant (STP) based on SBR technology, MPS (well sinking method) with the civil structure for 71.17 mld average flow for ultimate year including all electromagnetic works, rising main, 5 STPs IPS having capacity of 20.13 mld, 7.28 mld, 1.5 mld, 11.32 mld and 58.72 mld and all other appurtenant works followed by three months trial and run of all executed works in different wards of Karhera Zone.

End Date: August 9, 2023

Download PDF


Implementing Agency: Local Self Government Department, Government of Rajasthan

Segment: Sanitation and Sewerage

Work: The scope of work includes sewerage works in Pipar City, Rajasthan.

End Date: July 11, 2023

Download PDF


Implementing Agency: Jaysingpur Municipal Council (JMC)

Segment: Water Supply

Work: The scope of work includes design, supply, installation, testing and commissioning of automation system for raw water pumping machinery, water treatment plant (WTP), pure water pumping machinery including instrumentation, control valve, programmable logic controller (PLC) supervisory control and data acquisition (SCADA), electrical/electronics/mechanical/civil works with six years comprehensive Operation and Maintenance (O&M).

End Date: July 3, 2023

Download PDF


Implementing Agency: Bhubaneswar Development Authority (BDA)

Segment: Wastewater

Work: The scope of work includes survey, investigation, soil testing, preparation of comprehensive drainage master plan, project phasing, preparation of detailed project report (DPR), land acquisition support, statutory approval, bid process management and overall project monitoring.

End Date: September 21, 2023

Download PDF


Implementing Agency: Water Resources Department, Rajasthan

Segment: Water Supply

Work:  Package 1: Construction of Ramgarh barrage, Mahalpur barrage, Navnera pump house, rising main up to delivery cistern and delivery cistern with its O&M for a period of 10 yrs in Baran and Kota districts of the state (NGBI Link Package 1). The work is expected to be completed at an estimated cost of Rs 20,664.7 million.
Package 2: Construction of feeder with all structures from delivery cistern at Navnera barrage to submergence of Mez Anycut including construction of Aqueduct for crossing of Chambal river and operation and maintenance (O&M) for a period of 10 years in Kota and Bundi districts of the state (NGBI Link Package 2). The work is expected to be completed at an estimated cost of Rs 18,078.3 million.
Package 3: Construction of pump house with intake at Mez anycut, rising main, delivery cistern, tunnel and feeder drain up to submergence of Galwa dam, head work at Galwa, feeder up to Isarda dam submergence, Construction of pump house at bank of Galwa river, rising main up to delivery cistern for feeder to Bisalpur dam submergence including its O&M for a period of 10 years in Bundi and Tonk districts of the state (NGBI Link Package 3). The work is expected to be completed at an estimated cost of Rs 39,138.7 million.

End Date: August 28, 2023

Download PDF

Download PDF

Download PDF


Implementing Agency: Chandigarh Municipal Corporation (CMC)

Segment: Water Supply

Work: The scope of work includes renovation of the water treatment plant (WTP), primary distribution system, underground reservoirs, replacement of 270 Km out of 1013 Km distribution networks, which is approximately a 27 per cent substitution rate, expected upgrades of the distribution system will include bulk metering and supervisory control and data acquisition (SCADA) system, variable frequency derived (VFD) for pumps (to lower electricity consumption) and house service connections and customer meters will be replaced -176 000 water meters shall be replaced by automatic meter reading (AMR) meters and Operation and Maintenance (O&M) for 20 years. The project area is composed in six zones and 55 district metered areas (DMAs) (tentative), to be upgraded on a sequential basis under design, build and operate (DBO) basis.

End Date: December 16, 2023

Download PDF


Implementing Agency: Thane Municipal Corporation (TMC)

Segment: Wastewater

Work: The scope of work includes:
Sewerage : It includes preparation DPR and tender document for comprehensive improvement of existing sewerage system in TMC area.
Drainage: It includes preparation of DPR and tender document for drainage house connection in underground sewerage scheme (UGSS) – 1, 2 and 3 sewerage zones in TMC area and necessary branch line required for collection of sewerage from houses to main line.

End Date: June 22, 2023

Download PDF

Download PDF


Implementing Agency: Pune Municipal Corporation

Segment: Water Supply

Work: The scope of work includes design review, supervision and project management consultancy for balance works of implementation of equitable water supply system in newly merged 34 villages in Pune Municipal Corporation limits.

End Date: July 17, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water supply

Work: The scope of work includes survey, design, supply of all materials for construction of overhead tanks, clear water reservoirs, pump house, laying and joiniting of rising main, distribution system and SITC work of tubewells including PLC/SCADA automation work including commissioning, testing, trial run with defect liability (DLP).

End Date: July 17, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Wastewater

Work:  The scope of work includes the preparation of master plan and geographic information system (GIS) mapping for water supply and sewerage system management in Varanasi.

End Date: June 21, 2023

Download PDF


Implementing Agency: Rajasthan Urban Drinking Water Sewerage and Infrastructure Corporation Limited (RUDSICO)

Segment: Wastewater

Work: The scope of work includes:
Alwar: Providing, laying, jointing, testing and commissioning of sewerage system and all ancillary works along with design, construction, supply, installation, testing and commissioning including one-year defect liability period (DLP) with 10 years operation and maintenance (O&M) at an estimated cost of Rs 1,537.4 million.
Jaipur Heritage: Rehabilitation, replacement and upgradation of old and damaged existing sewerage system and all ancillary works, including one year DLP with 10 years O&M at an estimated cost of Rs 2,917.8 million.
Pali: Providing, laying, jointing, testing and commissioning of sewerage system and all ancillary works along with design, construction, supply, installation, testing and commissioning of civil, mechanical, electrical, instrumentation and other necessary works of sewage treatment plant (STP) with provision for treated wastewater reuse including one-year DLP with 10 years O&M at an estimated cost of Rs 652.2 million.

End Date: July 17, 2023

Download PDF

Download PDF

Download PDF


Implementing Agency: Public Health And Municipal Engineering Department, Telangana

Segment: Water Supply

Work: Package 1: It includes water supply in 10 ULBs which include Khanapur, Nirmal, Luxettipet, Naspur, Chennur, Kyathanpally, Mancherial, Bellampalle, Mandamarri and Adilabad at an estimated cost of Rs 3,573.13 million.
Package 2: It includes water supply in 15 ULBs which include Raikal, Dharmapuri, Jagtial, Korutla, Metpally, Choppadandi, Kothapally, Jammikunta, Huzurabad, Karimnagar, Sulthanabad, Manthani, Peddapalli, Sircilla and Vemulawada at an estimated cost of Rs 4,106.5 million.
Package 4: It includes water supply in 9 ULBs which include Wyra, Madhira, Sathupally, Dornakal, Marripeda, Thorruru, Mahaboobabad, Kothagudem and Manuguru ULBs at an estimated cost of Rs 2,266 million.
Package 5: It includes water supply in 15 ULBs which include Alampur, Waddepalle, Gadwal, Kosgi, Makthal, Narayanpet, Bhootpur, Jadcherla, Atmakur, Amarchinta, Kothakota, Pebbair, Wanaparthy, Nagarkurnool and Kalwakurthy at an estimated cost Of Rs 2,806.35 million.
Package 6: It includes water supply in 7 ULBs which include Banswada, Yellareddy, Kamareddy, Bheemgal, Bodhan, Armoor and Nizamabad at an estimated cost of Rs 3,670.67 million.
Package 7: It includes water supply in 11 ULbs which include Narsapur, Thoopran, Ramayampet, Medak, Narayankhed, Sangareddy, Zaheerabad, Sadasivpet, Cherial, Gajwel and Siddipet at an estimated cost of Rs 2,227.03 million.
Package 8: It includes water supply in 9 ULBs which include Kodangal, Parigi, Vikarabad, Tandur, Shankarpally, Amangal, Kothur, Shadnagar and Medchal at an estimated cost of Rs 1,535.39 million.
Package 9: It includes water supply in 17 ULBs which include Chityal, Chandur, Haliya, Nakrekal, Nandikonda, Nalgonda, Miryalguda, Nereducherla, Tirumalagiri, Kodada, Suryapet, Alair, Chotuppal, Mothkur, Pochampally, Yadagirigutta and Bhongir of Nalgonda Division at an estimated cost of Rs 3,467.47 million.

End Date: October 4, 2023

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF


Implementing Agency: Vizianagaram Municipal Corporation

Segment: Water Supply

Work: The scope of work includes the preparation of DPR which should be technically correct and should justify the project for technical feasibility, financial sustainability, environmental compatibility, social and political acceptability and legal and regulatory feasibility keeping the prospective future population, comprehensive planning, design for the whole town including future growth of town depending on the feedback from urban local bodies (ULB) and stakeholders.

End date: June 23, 2023

Download PDF


Implementing Agency: Uttarakhand Urban Sector Development Agency (UUSDA)

Segment: Water Supply

Work: The scope of services includes revalidation of water supply and sewer network design, construction of Tube well with the pumping station, laying of rising main from pumping station to service reservoirs, construction of overhead tanks (OHT)/ground level service reservoirs (GLSR) and ancillary works, development (laying and jointing) of distribution network on direct market access (DMA) basis, providing house connections with automatic meter reading (AMR) and installation of bulk flow meter capable of transmitting the data to central supervisory control and data acquisition (SCADA) system, setting out on site, laying of sewers, including providing of sewer house connections, construction of chambers, storm water, culverts, outfalls, rain water harvesting structures and Operation and Maintenance (O&M) of the water supply system, sewer network for 18 years.

End Date: July 10, 2023 (Package 2); July 11, 2023 (Package 3)

Download PDF

Download PDF


Implementing Agency: Jharkhand Urban Infrastructure Development Corporation Limited (JUIDCO)

Segment: Water Supply

Work: The scope of work involves survey, geographic information system (GIS) based consumer mapping, design, supply and construction of intake well, pump house, infiltration pipe gallery, vertical turbine pumps, centrifugal pump, RCC approach bridge/gangway, 21 million litres per day (mld) water treatment plant (WTP) and other allied infrastructure with five years of Operation and Maintenance (O&M).

End Date: June 26, 2023

Download PDF


Implementing Agency: Umarkhed Municipal Council

Segment: Water Supply

Work: The scope of work includes construction of intake well, jack well, overhead pump house, reinforced cement concrete (RCC) bridge, connecting main, approach bund, pure water rising main, pure water gravity main, RCC BPt, conventional water treatment plant (WTP) of 9.5 million litre per day (mld), elevated service reservoir and raw water pumping machinery VT pump.

End Date: June 12, 2023

Download PDF


Implementing Agency: Public Health Engineering Department, Rajasthan

Segment: Water Supply

Work: The scope of the project includes:
Nonera (Package 1) : It includes execution, testing and commissioning of intake well ,three water treatment plant (WTP), 3 concrete water recycling (CWR) and raw water rising main including 10 years of Operation and Maintenance (O&M) under Nonera Water Supply Project in Kota and Bundli districts at an estimated cost of Rs 2,322.5 million.
Parwana (Package 3) : It includes execution, testing and commissioning of WTP, pumping machinary , clear water mains, elevated service reservoir (ESR), CWRs ,cluster and village distribution , atomization, electrical works , functional house tap connection (FHTC) including 10 Years O&M under Parwan Water Supply Project in block Chhabra, Chhipabarod and Atru of District Baran at an estimated cost of Rs 10,238.1 million.

End Date: June 1, 2023

Download PDF

Download PDF


Implementing Agency: Rajasthan Urban Drinking Water Sewerage and Infrastructure Corporation Limited (RUDSICO)

Segment: Wastewater

Work: The scope of work includes providing, laying, jointing, testing and commissioning of sewerage system and all ancillary works along with design, construction, supply, installation, testing and commissioning of civil, mechanical, electrical, instrumentation and other necessary works of sewage pumping station (SPS) /MPS (if any), including 1 year defect liability with five years Operation and Maintenance (O&M).
These ULBs are:
Bikaner: It includes development of sewer system with one sewage treatment plant (STP) at an estimated cost of Rs 2,895.7 million.
Jaipur Heritage I: It includes development of sewer system with four new SPS and 3 MWPS at an estimated cost of Rs 3,179.5 million.
Sikar: It includes development of sewer system with two STPs at an estimated cost of Rs 1,478.4 million.
Jaipur Greater: It includes development of sewerage system at an estimated cost of Rs 4,800 million.

End Date: Bikaner: July 10, 2023; Jaipur Heritage I : July 19, 2023; Sikar: July 19, 2023; Jaipur Greater: July 10, 2023

Download PDF

Download PDF

Download PDF

Download PDF


Implementing Agency: Municipal Council Ner Nababpur

Segment: Water Supply; Wastewater

Work: The scope of work includes carrying out reconnaissance surveys, preparation of feasibility report, carrying out detailed survey, preparing proposal for getting requisite permissions from various concerned authority including preparation of detailed project report (DPR) of the project and assisting Maharashtra Jeevan Pradhikaran (MJP) for getting approvals from appraisal consultant, providing services for preparation of tender documents and bid process management including preparing proposal for getting requisite permissions from various concern authority, functioning as project management consultant & technical auditor of ‘Municipal Council Ner Nababpur’ for project execution, supervision and monitoring of Operation and Maintenance (O&M) and asset management for a period of a maximum one year.

End Date: May 30, 2023

Download PDF


Implementing Agency: Thane Municipal Corporation (TMC)

Segment: Water supply

Work: These packages are:

Package I: It includes improvement of water supply system in North Zone at an estimated cost of Rs 1,063.71 million.

Package II: It includes improvement of water supply system in Central and East Zone at an estimated cost of Rs 853 million.

Package III: It includes improvement of water supply system in North and Central Zone (Vatak Nagar and Lokamanya Nagar) at an estimated cost of Rs 570 million . The last date for bid submission is June 5, 2023.

End Date: June 21, 2023

Download PDF

Download PDF

Download PDF


Implementing Agency: Public Health and Municipal Engineering Department, Andhra Pradesh

Segment: Water Supply

Work: The scope of the project includes upgradation of water supply improvement scheme in Ongole Municipal Corporation with Ramatheertham balancing reservoir as source and performance based Operation and Maintenance (O&M) for five years including two years defect liability period (DLP).

End Date:  June 8, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Wastewater

Work: The scope of the project includes survey, investigation, design, operation and transfer of 43 million litres per day (mld) and 20 kld faecal sludge co-treatment at existing Salori STP campus along with associate infrastructure including interception, diversion and construction of two number sewage pumping station (SPS), effluent gravity pipeline, effluent rising main with manhole, tapping point at AB Culvert and raising of existing receiving chamber up to HFL near Bund of Salori STP operation and maintenance (O&M) period of 15 years under design, built operate and transfer (DBOT) mode.

End Date: July 17, 2023

Download PDF


Implementing Agency: Nagar Palika Parishad, Shivpuri

Segment: Water Supply

Work: The scope of the project includes providing, laying, joining of water pipeline along with programmable logic controller (PLC)-supervisory control and data acquisition (SCADA) in any of water supply components/sewerage pipeline of any material or nature like rising, feeder or distribution and construction of intake well/pump house, overhead tank or ground level reservoir.

End Date: June 28, 2023

Download PDF


Implementing Agency: Nagar Palika Nigam, Dewas

Segment: Water Supply

Work: The scope of work includes survey, soil investigation, design and construction of intake well, pump house, overhead tank, 30 million litre per day (mld) water treatment plant (WTP), house service connection, supervisory control and data acquisition system (SCADA) system and other related infrastructure.

End Date: June 30, 2023

Download PDF


Implementing Agency: Haryana State Industrial and Infrastructure Development Corporation (HSIIDC)

Segment: Wastewater

Work: The scope of work includes project management consultancy (PMC) bids for the IMT Kharkhoda Water Supply and Sewerage Project. HSIIDC is planning to develop infrastructure facilities such as water supply system, wastewater collection system, recirculation system of treated wastewater, storm water drainage (SWD) system, electrification, road network and other miscellaneous works at industrial model township (IMT), Kharkhoda in Sonepat district of Haryana at an estimated cost of Rs 7,764.4 million

End Date: July 3, 2023

Download PDF


Implementing Agency: Ratlam Nagar Palika

Segment: Water Supply

Work: The scope of the project includes providing, laying, and jointing of water pipeline of any material or nature like rising, feeder or distribution, construction of 12 million litre per day (mld) water treatment plant (WTP) and construction of intake well/pum[p house, an overhead tank of ground-level service reservoir.

End Date: June 0, 2023

Download PDF


Implementing Agency: Bhisi Nagar Panchayat

Segment: Water Supply

Work: The scope of the project includes construction of jack well (by sinking method), approach bridge, raw water rising main, raw/pure water pumping machinery, raw/pure water gravity/rising main, un-conventional water treatment plant (WTP) including compound wall, elevated storage reservoirs (ESR), master balance reservoir (MBR) , distribution system, supervisory control and data acquisition (SCADA) -automation, miscellaneous works and trial and run.

End Date: June 5, 2023

Download PDF


Implementing Agency: Wadi Municipal Council

Segment: Wastewater

Work: The scope of the work includes working survey, sewerage network , nallha interceptor & divergence (I&D) work, household connection , utility shifting, wet well with overhead pump house, pumping machinery, sewage pumping machinery with submersible sewage pumps, sewerage treatment plant (STP), road reinstating, annual Operation and Maintenance (O&M) for one year.

End Date: June 2, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of the project includes surveying, soil investigation, design , testing, trail and run, commissioning, testing of water supply pipeline and associated works along with water supply utility shifting works at Chaudahkosi Parikarma Marg in Ayodhya district.

End Date: May 15, 2023

Download PDF


Implementing Agency: Municipal Corporation of Rewa

Segment: Water Supply

Work: The scope of the project includes survey, soil investigation, design and execution of various works for augmentation of water supply system including construction of an intake well, raw water pump house, installation of raw/ clear water pumps, substation including 33kv high tension (HT) feeder, water treatment plant, elevated service reservoir (ELSR) and ground-level storage reservoir (GLSR), providing, laying, jointing, testing and commissioning of raw/clear water pumping/feeder main and distribution network including excavation, refilling, road cutting /dismantling, restoration to its original condition, providing and fixing required valves (sluice, air, scour, pressure reducing valve (PRV) etc. specials, fittings, flowmeters. construction of valve chambers, thrust blocks and house service connections, automation supervisory control and data acquisition (SCADA).

End Date: May 24, 2023

Download PDF


Implementing Agency: Faridabad Municipal Corporation

Segment: Wastewater

Work: The scope of the project includes revamping of sewerage system in Faridabad (Phase – I) including rehabilitation of the existing lines using cured-in-place pipe (CIPP) liner.

End Date: June 1, 2023

 Download PDF


Implementing Agency: Public Work Department, Delhi

Segment: Wastewater

Work: The scope of work includes preparation of a detailed project report (DPR) within six months, one year of project execution, one year of solution validation and overall project supervision.

End Date: May 10, 2023

Download PDF


Implementing Agency: Delhi Jal Board

Segment: Wastewater

Work: The scope of work includes the construction of decentralized STP and sewage pumping station (SPS) at Punjab Khor, Jat Khor, Auchandi and Qutubgrah along with other associated works on hybrid annuity mode (HAM) with10 years of Operation and Maintenance (O&M) and two years defect liability Period (DLP).

End Date: May 29, 2023

Download PDF


Implementing Agency: Chhatrapati Sambhajinagar Municipal Corporation

Segment: Wastewater

Work: The scope of work includes construction of underground drainage system (UGDS) for Satara Deolai area at Chhatrapati Sambhajinagar, Maharashtra.

End Date: June 8, 2023

Download PDF


Implementing Agency: Umarkhed Municipal Council

Segment: Water Supply

Work: The scope of work includes construction of intake well, jack well, overhead pump house, reinforced cement concrete (RCC) bridge, connecting main, approach bund, pure water rising main, pure water gravity main, RCC BPt, conventional water treatment plant (WTP) of 9.5 million litre per day (mld), elevated service reservoir and raw water pumping machinery VT pump.

End Date: May 15, 2023

Download PDF


Implementing Agency: Madhya Pradesh Urban Development Company Limited (MPUDC)

Segment: Wastewater

Work: The scope of work includes improvement of the wastewater management system in Sanchi Nagar Parishad in Raisen district under the Madhya Pradesh Urban Services Improvement Project -Additional Financing Package 1F

End Date: May 19, 2023

Download PDF


Implementing Agency: Jharkhand Urban Infrastructure Development Corporation Limited (JUIDCO)

Segment : Water Supply

Work: The scope of work includes augmentation and strengthening of water supply scheme for Ramgarh Nagar Parishad including cantonment board Ramgarh.

End Date: June 1, 2023

Download PDF


Implementing Agency: Bihar Urban Infrastructure Development Corporation Limited (BUIDCO)

Segment : Water Supply

Work: The scope of work includes construction of an elevated service reservoir (ESR), seven overhead tanks (OHT), a distribution network of 96.68 km and 1400 service connections, 12 high-yielding tubewell, raw water pump set, clear water pipeline of 20.1 km at Barun, a Gangway -I set, lifting arrangement, chlorinator of 200 litres, master elevated reservoir of 1270 kilolitres, intermediate pumping station for Zone – III, V and VI, SCADA system and other related infrastructure.

End Date: May 16, 2023

Download PDF


Implementing Agency: Tamil Nadu Water Supply and Drainage Board (TWAD)

Segment : Wastewater

Work: The scope of work includes:
In Zone V, construction of STP having a capacity of 15.43 million litres per day (mld) on design, build operate (DBO) basis in Vadavalli and Veerakeralam area for wards 16 to 19.
In zone VII, construction of STP having a capacity of 19.49 mld on a DBO basis for Kavundampalayam and Thudiyalur area for wards part 1, 2 to 9 and 43.

End Date: June 1, 2023

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment : Water Supply

Work: The scope of work includes topographical and hydrographic survey for surface water-based piped water supply scheme of Chanchal-I, Ratua-I and Ratua-II block at Fulhar River as intake point near Nakkati Ghat Bridge, Balupur in Malda Division, West Bengal

End Date: May 3, 2023

Download PDF


Implementing Agency: Andaman Public Work Department (APWD), Port Blair

Segment: Wastewater

Work: The scope of work includes development of Storm Water Drainage (SWD) system for area-based development (ABD) areas in Port Blair under the Smart City Mission.

End Date: July 21, 2023

Download PDF


Implementing Agency: Uttarakhand Urban Sector Development Agency (UUSDA)

Segment: Wastewater

Work: The scope of work includes survey, soil investigation, design, drawing, documentation work of pipeline, supply, laying, testing and commissioning of the sewer network, an appurtenance of pipes with manholes, ventilating shaft, construction manholes, intermediate sewage pumping stations, rising main, house connections followed with operation and maintenance (O&M) for five years.

End Date: June 6, 2023

Download PDF


Implementing Agency: Uttarakhand Urban Sector Development Agency (UUSDA)

Segment: Wastewater

Work: The scope of work includes survey, soil investigation, design, drawing, documentation work of pipeline, supply, laying, testing and commissioning of the sewer network, an appurtenance of pipes with manholes, ventilating shaft, construction manholes, intermediate sewage pumping stations, rising main, house connections followed with operation and maintenance (O&M) for five years.

End Date: June 5, 2023

Download PDF


Implementing Agency: Chandigarh Municipal Corporation (CMC)

Segment: Water Supply

Work: The scope of work includes long-term technical assistance for the 24X7 Manimajra Water Supply Project in Chandigarh. The request for proposal (RFP) has been issued to the following shortlisted consultants: Joint Venture (JV) of InfraEn India Private Limited and NJS Energy India Private Limited; JV of Shah Technical Consultants Private Limited, Alereo and Crisil Risk and Infrastructure Solutions;JV of STUP Consultants Private Limited and Ceinsys Tech Limited;JV of Tata Consulting Engineers and Antea France and Antea India Private Limited; JV of URS Scott Wilson Private Limited, DRA Consultants and AECOM India; JV of Sai Consultants Engineers, Z and A Antonaropoulos and Associates and Nippon Koel.

End Date: July 6, 2023

Download PDF


Implementing Agency:  Uttar Pradesh Jal Nigam (UPJN)

Segment: Wastewater

Work: The scope of work includes survey, investigation, design, supply, laying, commissioning and testing of sewer pipe in lateral/branch sewers and balance house connection & road reinstatement & its appurtenant works in sewerage district 3 Part 1 Phase 1 of Lucknow city.

End Date: May 5, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of the project includes surveying, soil investigation, design , testing, trail and run, commissioning, testing of water supply pipeline and associated works along with water supply utility shifting works at Chaudahkosi Parikarma Marg in Ayodhya district.

End Date: May 3, 2023

Download PDF


Implementing Agency: Madhya Pradesh Urban Development Company Limited (MPUDC)

Segment: Water Supply

Work: The scope of work includes improvement of water supply systems in Barigarh and Chandla Nagar Parishads Chhatarpur district and Ajaygarh and Devendranagar Nagar Parishads in Panna District.

End Date: May 19, 2023

Download PDF


Implementing Agency: Bhiwandi Nizampur City Municipal Corporation

Segment: Water Supply

Work: The scope of the project includes construction of jackwell, overhead pump house, retaining wall, sub station, reinforced cement concrete (RCC) bridges, raw water and pure water rising mains, two conventional water treatment plants (WTPs) having capacities of 123 million litre per day (mld) and 53 mld, RCC Sumps, RCC master balancing reservoir (MBR)/ elevated service reservoir (ESR)/Ground Service Reservoir (GSR), DI leading mains and other miscellaneous work.

End Date: June 7, 2023

Download PDF


Implementing Agency: Department of Drinking Water and Sanitation, Uttarakhand

Segment: Wastewater

Work: The scope of work includes supplying, laying, jointing, constructing, testing, commissioning of sewerage networks, house service connections and sewage pump stations.

End Date: May 18, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Wastewater

Work: The scope of work includes survey, investigation, design, supply, laying, commissioning and testing of sewer pipe in lateral/branch sewers and balance house connection & road reinstatement & its appurtenant works in sewerage district 3 part 2 of Lucknow city.

End Date: May 22, 2023

Download PDF


Implementing Agency: Pauni Municipal Council

Segment: Wastewater

Work: The scope of work includes a working survey, collection system, manhole pumping station, sump, rising main, sewage pumping station, mechanical works of pumping station, automation for the pumping station, express feeder, sewerage treatment plant (STP) of capacity 5 million litre per day (mld) – sequential batch reactor (SBR), effluent storage tank, compound wall, house service connection, utility shifting, road restoration, special purpose vehicle mounted combination of suction cum jetting machine, trial and run for three months, miscellaneous work and push through.

End Date: April 12, 2023

Download PDF


Implementing Agency: Nagar Parishad Pali

Segment: Wastewater

Work: The scope of work includes preparation of DPR, survey work for sewerage work in remaining leftover areas and recycling and reuse of treated water in Pali town.

End Date: April 12, 2023

Download PDF


Implementing Agency: Bihar Urban Infrastructure Development Corporation Limited (BUIDCO)

Segment: Water Supply

Work: The scope of work includes the construction of water supply system providing full coverage to 35 partially covered wards of Darbhanga Nagar Nigam including five years of Operation and Maintenance (O&M).

End Date: April 21, 2023

Download PDF


Implementing Agency: Bihar Urban Infrastructure Development Corporation Limited (BUIDCO)

Segment: Sewerage

Work: The scope of the work includes construction of two sewerage treatment plants (STPs) having capacities of 11 million litre per day (mld) each along with UV disinfection controlled with supervisory control and data acquisition (SCADA) including survey, review, redesign wherever necessary, building 2116 m interception drain tapping of 3 drains, screens and mechanically operated gates facilitating effluent channel disposal of the treated effluent channel of treated effluent through 224 m pipeline and operation and maintenance (O&M) of 15 years.

End Date: May 10, 2023

Download PDF


Implementing Agency: Karnataka Neeravari Nigam Limited invited

Segment: Water Supply

Work: The scope of work includes survey, investigation, design, supply, erection, testing and commissioning of diversion dam across Kalasa Nala, jack well cum pump house on the foreshore, rising main (MS Pipe) from jack-well to Kalasa Inter-Connecting Canal along with design supply installation, testing and commissioning of pumping machinery with 11KV motors, 110KV/11KV substation, 110KV power transmission line, overhead reservoir tank (OHT)/underground cable, construction of diversion dam across Haltara nala, jack well cum pump house on the foreshore, rising main (MS pipe) from jack well to Kalasa dam along with design, supply, installation, testing and commissioning of pumping machinery, 11kv/6.6kv substation, 11kv transmission line (ug cable). (3) construction of 8 nos. of diversion weirs across tributaries of Surla Nala, gravity main (ms pipe) linking all the weirs and leading to collection sump (receiving chamber), jack well cum pump house including rising main (ms pipe) from sump to Kalasa dam along with design, suAugust 21, 2023pply, installation, testing and commissioning of pumping machinery, 11kv/0.433kv substation, 11kv transmission line (ug cable) and other civil works of cut and cover portion, supply of spare parts, tools including requisite manpower followed by operation and maintenance (O&M) of the system for five years from the date of completion on turnkey basis.

End Date: August 21, 2023

Download PDF


Implementing Agency: Ulhasnagar Municipal Corporation

Segment: Wastewater

Work: Working survey, design and construction of Sewerage Collection system in Khemani Zone, Shantinagar Zone, Khadegolvali Zone, Vadolgaon Zone, house sewer connection work, sewage treatment plant having capacity of 19.50 million litres per day (MLD) for Shantinagar Zone, electrical work, road restoration and railway crossings by micro tunnelling methods work including complete test and trial. The work is likely to be completed in 730 days at an estimated cost of Rs 3500.32 million.

End Date: April 20, 2023

Download PDF


Implementing Agency:  Ulhasnagar Municipal Corporation

Segment: Water Supply

Work: Design, provide and construction of pure water transmission main, construction of reinforced cement concrete (RCC) elevated service reservoir (ESR), dismantling of existing ESR, distribution system in north and south side, utility shifting, consumer survey of all properties, domestic water meter’s, house Connections, water audit of transmission and distribution system and ultrasonic flow meter and other related works followed by complete test an trial. The work is likely to be completed in 545 days at an estimated cost of Rs 1014.26 million.

End Date: May 11, 2023

Download PDF


Implementing Agency: Mehkar Municipal Corporation

Segment: Water Supply

Work: The scope of work includes construction of intake well, connecting main, inspection well, jack well, approach bridge, raw water rising main, break pressure tank, raw/pure water pumping machinery, raw/pure water gravity/rising main, conventional water treatment plant (WTP) including compound wall, elevated/ground storage reservoirs, distribution system, miscellaneous works and trial and run etc.

End Date: April 8, 2023

Download PDF


Implementing Agency: Rajasthan Urban Drinking Water Sewerage and Infrastructure Corporation Limited (RUDSICO)

Segment: Wastewater

Work: The scope of work includes:

Jodhpur North- I and South – I: Upgradation of Sewage treatment plant (STP) of 50 million litre per day (mld) capacity at Salawas Jodhpur along with design, supply, installation, testing and commissioning including one year of defect liability period (DLP) and 10 years of operation and maintenance (O&M) at an estimated cost of Rs 1234.7 million.

Bikaner: Replacement of old and damaged existing sewerage system along with laying of new sewerage system and all ancillary works along with Design, Construction, supply, Installation, testing and commissioning (Civil, Mechanical, electrical, instrumentation & other necessary works) of Sewage Pumping Station/MWPS (if any), Sewage Treatment Plant based on SBR Process with provision for treated waste water reuse including 1 year defect liability and 10 years O&M for Bikaner town at an estimated cost of Rs 2895.7 million.

Jodhpur South II: Replacement of old and new sewer system at an estimated cost of Rs 1926.1 million.

Jodhpur North II: Replacement of old and new sewer system with 2 new sewage pumping station (SPS) at an estimated cost of Rs 1413.7 million.

Jhalawar: Development of Sewer System with one STP at an estimated cost of Rs 838.4 million.

Tonk: Development of Sewer System with 6 STPs, 2 MWPs and Sewerage network at an estimated cost of Rs 1075.6 million.

End Date: May 4, 2023

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF


Implementing Agency: Shegaon Municipal Council

Segment: Wastewater

Work: The scope of work includes laying of RCC and HDPE trunk main pipes, construction of pumping station (wet well with overhead pump house), rising main, sewerage treatment plant (STP) of 8.5 million litre per day (mld) and 2.5 mld based on sequential batch reactor (SBR) technology, RCC Sump and railway and road crossing by push through method.

End Date: March 30, 2023

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water  Supply

Work: The scope of work includes developing, establishing contact and geo-spatial platform with centralized water information management system (WIMS) covering five blocks of Purulia district

End Date: April 25, 2023

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water Supply

Work: The scope of work involves laying of clear water transmission main from existing water treatment plants (WTPs) in Mathurapur and Dariapur to different zonal overhead reservoirs (OHR) sites of Manikchak and Kaliachak-III Block, construction of Overhead Reservoir on pile or raft foundation based on soil test report, laying of distribution system and functional house tap connection (FHTC) in Manikchak, Englishbazar, Kaliachak-I,II & III Blocks in the district of Malda.

End Date: April 18, 2023

Download PDF


Implementing Agency: Karnataka Urban Water Supply And Drainage Board (KUWSDB)

Segment: Water Supply

Work: The scope of the project includes a detailed survey, design (hydraulic and Structural), construction, supply, installation, testing and commissioning of intake well, inspection chamber, connecting pipe, rejuvenation of Jackwell cum pump house, rejuvenation of 15MLD capacity WTP, strengthening of Raw / pure water raising main in initial stretches, Providing feeder mains, Construction of Service reservoirs, Electromechanical works (pumping machineries and allied works), distribution network with house service connection works and operation and maintenance (O&M) of five years.

End Date: April 12, 2023

Download PDF


Implementing Agency: Umarkhed Municipal Council

Segment: Water Supply

Work: The scope of work includes construction of intake well, Jack well, overhead pump house, reinforced cement concrete (RCC) bridge, connecting main, approach bund, pure water rising main, pure water gravity main, RCC BPt, conventional water treatment plant (WTP) of 9.5 million litre per day (mld), elevated service reservoir andraw water pumping machinery VT pump.

End Date: April 3, 2023

Download PDF


Implementing Agency: Pauni Municipal Council

Segment: Wastewater

Work: The scope of work involves post-tender and pre-award activities along with project management and construction/associate supervision.

End Date: March 20, 2023

Download PDF


Implementing Agency: Water Resource Department, Rajasthan

Segment: Water Supply

Work: The scope of the project includes

Sabarmati: Construction of a concrete gravity dam having a gross storage capacity of 66.92 Mcum along with a rockfill dam, coffer dam, intake structure and tunnel from the dam across Sabarmati river to Dam across Sei River including Civil/ Electrical/ Hydro Mechanical, instrumentation works near Chak Sandmariya village of Tehsil Kotra, Udaipur District including planning, geotechnical and other investigation, design, drawing and execution complete for drinking water Project. The estimated cost of the project is Rs 5,199.6 million.

Sei: Construction of a concrete gravity dam having a gross storage capacity of 66.92Mcum along with a rockfill dam, coffer dam, intake structure and tunnel from the dam across the Sei River to the pump house including civil/ electrical, instrumentation works near Buja village of Tehsil Kotra, Udaipur District including planning, geotechnical and other investigation, design, drawing and execution complete for drinking water Project. The estimated cost of the project is Rs 5,741.8 million.

End Date: April 18, 2023

Download PDF

Download PDF


Implementing Agency: Ichalkaranji Municipal Corporation

Segment: Water Supply

Work: The scope of the work includes the construction of head works at Dudh Ganga river, forebay, head works, pump house overhead works, powerhouse, approach bridge near head works, reinforced cement concrete (RCC) weir (check dam) at Dudh Ganga river, raw water pumping machinery, raw water rising main from head works at Dudh Ganga river to BPT at Yalgud, etc.

End Date: March 20, 2023

Download PDF


Implementing Agency: Mhaswad Nagar Parishad

Segment: Water Supply

Work: The scope of the work involves a working survey, repair of jack well and pump houses, meter room for headwork and solar, approach road, raw water rising main, strengthening of existing MS, the pipeline of 12.115 km from HW to the water treatment plant (WTP), 4.5 mld WTP, renovation of 3.5 mld WTP, staff quarter at jack well and 2 WTOs, pure water gravity main, elevated service reservoirs, repair to existing ESR and other related works.

End Date: March 21, 2023

Download PDF


Implementing Agency: Mumbai Metropolitan Region Development Authority (MMRDA)

Segment: Water Supply

Work: The scope of work includes preparation of DPR and feasibility report for utilization of water from Deharji Dam for providing drinking water facility to Mumbai Metropolitan Region.

End Date: April 10, 2023

Download PDF


Implementing Agency: Haryana State Industrial and Infrastructure Development Corporation (HSIIDC)

Segment: Wastewater

Work: The scope of work includes PMC services for the development of infrastructure facilities i.e. road network, water supply system, wastewater collection system, recirculation system of treated waste water, stormwater drainage system, utility tunnel, landscaping, fire fighting system, electrification and street lighting and all other works contingent there to including trial run for 3 months. thereafter, 60 months of defect liability period (DLP) including 60 months of operation & maintenance of all infrastructure during DLP.

End Date: April 12, 2023

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water Supply

Work: Ths scope of work includes sinking of tube well, construction of different capacity reinforced cement concrete (RCC), over head reservoir, over pile / raft foundation including sub soil investigation works for construction of over head reservoir with laying distribution system, pump house, boundary wall and providing 33066 functional household tap connection (FHTC) for Kasba Narayangarh, Khursi, Naharpur, Narma, Pakurseni, Asti, Bara Mahanpur, Gobindapur Brahman Sasan, Jamuna, Reripur, Tutranga, Shujanagar and Gokulpur Pipe water supply Scheme within Narayangarh Block including Operation & maintenance (O&M) under Kharagpur sub division of Midnapore division under Paschim Medinipur District.

End Date: May 15, 2023

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water Supply

Work: The scope of project includes sinking of tube well, construction of different capacity rcc over head reservoir over pile / raft foundation including sub soil investigation works with laying distribution system, pump house and providing functional household tap connection (41827 nos), etc. for 32 nos pipe water supply scheme.

End Date:April 25, 2023

Download PDF


Implementing Agency: Irrigation Research Institute, Government of Uttarakhand

Segment: Wastewater

Work: The scope of work includes primarily preparing a DPR for the Drainage Plan of stormwater and sewage water and other related services in Gopeshwar town, Chamoli, Uttarakhand.

End Date: March 27, 2023

Download PDF


Implementing Agency: Panvel Municipal Corporation

Segment: Water Supply

Work: Survey, construction of sump well, installation of pumping machinery, tapping connections & providing, lowering & laying of transmission line, rising main, distribution system network, designing and constructing of reinforced cement concrete  (RCC), membrane bioreactor (MBR), ground service reservoir (GSR) and elevated storage tank (ESR), road restoration work etc. including test and trial at an estimated cost of Rs 1,231.43 million

End Date: April 24, 2023

Download PDF


Implementing Agency: Panvel Municipal Corporation

Segment: Sewerage

Work: Survey, design and construction of a prefabricated sewage pumping station, prefabricated treatment plant, sewage treatment plant, installation of pumping machinery, providing, lowering & laying of collection system (sewer network), pumping main, road restoration work etc. including test and trial at an estimated cost of Rs 1,714.9 million.

End Date: March 23, 2023

Download PDF


Implementing Agency: Khandwa Municipal Corporation

Segment: Water Supply

Work: The scope of work involves- survey, soil investigation, design and execution of various works for augmentation of water supply system including water treatment plant having capacity 13.65 mld. construction of 5 ESR with providing, laying, jointing, testing and commissioning of clear water pumping main and feeder main, within the city limit and distribution network including excavation, refilling, road cutting /dismantling, restoration to its original condition, providing and fixing required valves (sluice, air, scour, and PRV etc.). Specials, fittings, flow meters. Construction of valve chambers, thrust blocks. 2500 House service connections, Automation (PLC-SCADA for WTP, ESR and module distribution zone) complete as required as per scope of work. Preparing the Module Zone (DMA) for 24×7 metered water supply as per the directives of the Municipal Commissioner etc. all complete.

End Date: August 24, 2023

Download PDF


Implementing Agency: Madhya Pradesh Urban Development Company Limited (MPUDCL)

Segment: Wastewater

Work: The scope of work involves- balance works of survey, review the designs, redesign where necessary and build sewage collection and conveyance system, sewage treatment and disposal system of Sendhwa Nagar Palika, district Barwani in Madhya Pradesh.

End Date: April 11, 2023

Download PDF


Implementing Agency: Madhya Pradesh Urban Development Company Limited (MPUDCL)

Segment: Wastewater

Work: The scope of work involves- balance works of survey, review the designs, redesign where necessary and build sewage collection and conveyance system, sewage treatment and disposal system of Barwani Nagar Palika, district Barwani in Madhya Pradesh.

End Date: April 11, 2023

Download PDF


Implementing Agency: Delhi Jal Boards (DJB)

Segment: Wastewater

Work: The scope of work includes providing, laying and jointing 300 mm to 560 mm dia internal/ peripheral sewer lines under the command of Auchandi DSTP and under the command of Qutubgarh DSTP in Bawana AC

End Date: March 14, 2023

Download PDF


Implementing Agency: Tamil Nadu Water Supply and Drainage Board (TWAD)

Segment: Water Supply

Work: The project aims to supply water to Rasipuram municipality, eight town panchayats and certain other rural habitations in Namakkal district in three packages: Package I, II and III which are being implemented at a cost of Rs 2,260 million, Rs 2,550 million and Rs 2,200 million, respectively. It is likely to be completed in 18 months with six months of trial run period and 60 months of maintenance period.

End Date: March 7, 2023

Download PDF

Download PDF

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water Supply

Work: The project involves sinking of tube well, construction of different capacity reinforced cement concrete (RCC) over head reservoir over pile /raft foundation including sub soil investigation works with laying distribution system, pump house and providing functional household tap connection (32862 Nos) for 21 nos pipe water supply scheme including two years Operation and Maintenance (O&M) in Moyna and Contai -I block Under Tamluk Division in Purba Medinipur District.

End Date: March 28, 2023

Download PDF


Implementing Agency: Uttar Pradesh Irrigation Department

Segment: Water Supply

Work: The scope of the project includes construction of slope cement concrete (CC) lining and other works from 215.5 to 228.2 of UGC for 43 cusec water supply to THDC Khurja.

End Date: February 25, 2023

Download PDF


Implementing Agency:  Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of work includes construction of an overhead tank, pump house, staff quarter, boundary wall, gate, site development, supply, laying and jointing of rising main main, distribution system and renovation of existing facilities including PLC supervisory control and data acquisition (SCADA) automation of all tubewells as per specifications in all respects including commissioning, testing, trial & defect liabilities and run, handing over the complete works on turn-key basis.

End Date: April 10, 2023

Download PDF


Implementing Agency: Mira Bhaindar Municipal Corporation (MBMC)

Segment: Water Supply and Wastewater

Work: The scope of work includes:

Water Supply: Augmentation of MBMC water supply scheme to the Surya at MBMC area as the source. The work is likely to be completed in 24 months at an estimated cost of Rs 4,235.43 million.

Sewerage: Development of underground sewerage system phase -II  of Part – I in MBMC area. The work is likely to be completed in 24 months at an estimated cost of Rs 1,470.55 million.

End Date: May 9, 2023.

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of the project includes detailed survey of existing status of water supply components, including distribution network, formation of zones/distrcit metre areas, construction of tube wells including PLC supervisory control and data acquisition (SCADA) automation of all tubewells, supply and installation of flow metres in zone /district metre areas, setting up of baseline levels for 24×7 water supplies, laying replacement of 92 km of new distribution DI pipeline to attain minimum terminal pressure of 21 m along with new/shifting house service connections, rehabilitation of feeder mains and rising main,  supply and installation of AMR water metres at both existing and new houses, overhead tanks of varying capacities (1300 kl, 2400kl, 1900 kl), rehabilitation of existing GSR, oHT and pump houses, supply and installation of isolation valves, FCV, PCV, bulk metres, level sensors, chlorine detector etc, establishment of SCADA system, development of computerized billing system.

End Date: March 31, 2023

Download PDF


Implementing Agency: Municipal Corporation of Rewa

Segment: Water Supply

Work: The scope of the project includes survey, soil investigation, design and execution of various works for augmentation of water supply system including construction of an intake well, raw water pump house, installation of raw/ clear water pumps, substation including 33kv high tension (HT) feeder, water treatment plant, elevated service reservoir (ELSR) and ground-level storage reservoir (GLSR), providing, laying, jointing, testing and commissioning of raw/clear water pumping/feeder main and distribution network including excavation, refilling, road cutting /dismantling, restoration to its original condition, providing and fixing required valves (sluice, air, scour, pressure reducing valve  (PRV) etc. specials, fittings, flowmeters. construction of valve chambers, thrust blocks and house service connections, automation supervisory control and data acquisition (SCADA).

End Date: April 28, 2023

Download PDF


Implementing Agency: Rajasthan Urban Drinking Water Sewerage and Infrastructure Corporation Limited (RUDSICO)

Segment: Wastewater

Work: The scope of the project involves providing, laying, jointing, testing and commissioning of sewerage system and all ancillary works along with design, construction, supply, installation, testing and commissioning (civil, mechanical, electrical, instrumentation and other necessary works) of sewage pumping station (SPS)/MPS (if any), sewage treatment plant (STP) based on sequential batch reactor (SBR) process with provision for treated waste water reuse including one year defect liability with 10 years of operation and management (O&M) for areas under six packages.

The works in these ULBs are:

Bhilwara (Package 7): Construction of sewer system with one and sewerage network at an estimated cost of Rs 2,294.1 million.

Chittorgarh (Package 8): Construction of sewer system with two STPs and sewerage network at an estimated cost of Rs 955.6 million.

Gangapur city and Sawai Madhopur (Package 9) : Construction of sewer network with one new STP in both areas and sewerage network at an estimated cost of Rs 1,487.3 million.

Sringanganagar and Jhunjhunu (Package 10):  Construction of sewer network with 2 new STPs, 3 MWPS in Sriganaganagar and a new STP and upgradation of a STP in Jhunjhunu and sewage networks at an estimated cost of Rs 1,954.9 million.

Kishangarh(Package 11): Construction of a new Stp, one SPS and sewrage network at an estimated cost of Rs 1,013 million.

Bharatpur (Package 12): Construction of sewer system with three new SPS, upgradation of one SPS and sewerage network at an estimated cost of Rs 1,209.7 million.

End Date: March 15, 2023

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF


Implementing Agency: Public Health Engineering Department, Haryana

Segment: Wastewater

Work: The scope of the work includes survey, investigation, DPR, detailed notice inviting tender (DNIT), construction supervision and contract management for the works relating to water supply, sewerage, septage management, sewerage treatment plant (STP), rejuvenation of water bodies and parks / green space development management as per the guidelines of Atal Mission for Rejuvenation and Urban Transformation (AMRUT) 2.0 and PHED guideline for Gurugram city and Manesar town.

End Date: March 6, 2023

Download PDF


Implementing Agency: Public Health Engineering Department (PHED), Haryana

Segment: Wastewater

Work: The scope of work includes survey, studies, investigation, preparation of feasibility report, detailed project report (DPR), detailed notice inviting tender, construction supervision and contract management for works relating to water supply, sewerage, storms, sewage treatment plant (STP), common effluent treatment plant (CETP), reuse of treated wastewater etc. in Bhiwani City, Dadri, Badhra, Bawani Khera, Siwani, Loharu and Tosham in Bhiwani Circle.

End Date:  February 22, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of work includes survey, soil investigation, design, supply of all materials for construction, erection, completion, testing and commissioning of water supply works such as reinforced cement concrete (RCC) overhead tanks (OHTs), pumping station, rising main, feeder main distribution system, SCADA room, chlorination room, meter room, panel room and other site development works with a trail run of 6 months and defect liability period (DLP) of 12 years.

End Date: May 9, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of work includes survey, design, supply of all materials for construction of overhead tanks, clear water reservoirs, pump house, laying and joiniting of rising main, distribution system and SITC work of tubewells including PLC/SCADA automation work including commissioning, testing, trial run with defect liability (DLP).

End Date: March 4, 2023

Download PDF


Implementing Agency: Guwahati Metropolitan Development Authority (GMDA)

Segment: Water Supply

Work: The scope of work includes balance civil , mechanical and electrical works of the plant and balance gap closing and damaged portion of pipelines in 40 district metering areas (DMAs) of Jalukbari, Ganeshpura (East), Ganeshpura (West), Gabeshpura (Central), Borjhar and Mirzapor distribution zones of the project.

End Date: April 18, 2023

Download PDF


Implementing Agency: Uttarakhand Urban Sector Development Agency (UUSDA)

Segment: Water Supply

Work: The scope of the project involves development of 24×7 water supply, wastewater management, urban drainage, urban landscaping, urban roads and transport and other works in Rishikesh, Muni ke Reti, Swargashram and Tapovan towns in Rishikesh.

End Date: March 20, 2023

Download PDF


Implementing Agency: Water Corporation of Odisha (WATCO)

Segment: Wastewater

Work: Consultancy works for providing Authority’s Engineer (AE) services for supervision of the construction of water treatment plant (WTP) in Bhubaneshwar, Odisha.

End Date: February 27, 2023

Download PDF


Implementing Agency: Ludhiana Municipal Corporation

Segment: Wastewater

Work: The scope of work includes the preparation of a service improvement plan (SIP) (including Survey, Investigation, condition assessment, methodology for project execution, design submissions, approval, etc), design, construction and commissioning of the project components including continual designs submissions and approval as per the project methodology approved during SIP preparation) based on the scope defined in this tender and Defect Liability Period (DLP) of 10 years.

End Date: April 12, 2023

Download PDF


Implementing Agency: Jharkhand Urban Infrastructure Development Corporation Limited (JUIDCO)

Segment: Water Supply

Work: Augmentation and strengthening of water supply scheme for Ramgarh Nagar Parishad including cantonment board Ramgarh.

End Date: June 8, 2023

Download PDF


Implementing Agency: Kerala Water Authority (KWA)

Segment: Water Supply

Work: The scope of work includes water supply upgradation and operation and management work in Kochi.

End Date: May 12, 2023.

Download PDF


Implementing Agency: Public Health Engineering Department (PHED)

Segment: Wastewater

Work: The scope of work includes survey, studies, investigation, preparation of feasibility report, detailed project report (DPR), detailed notice inviting tender, construction supervision and contract management for works relating to water supply, sewerage, storms, sewage treatment plant (STP), common effluent treatment plant (CETP), reuse of treated wastewater etc. in Ambala Sadar, Ambala City, Naraingarh, Sadhoura, Kalka, Pinjore, Yamuna Nagar, Jagadhari, Radaur in Ambala Circle.

End Date: February 27, 2023

Download PDF


Implementing Agency:  Faridabad Municipal Corporation

Segment: Wastewater

Work: PMC work for the rehabilitation of the Sewerage system (Phase -I) in Faridabad, Haryana

End Date: June 8, 2023

Download PDF


Implementing Agency: Karnataka Urban Water Supply And Drainage Board (KUWSDB)

Segment: Water Supply

Work: The scope of work includes survey, design, construction, supply, installation, testing and commissioning of submersible centrifugal or suitable raw water pump sets in allocated bay of pavgada medium velocity water spray system (MVWSS) jack well cum pump house; water treatment plant (WTP)- plate settlers & v-wire under-drain system rapid sand filtration system, automation, raw/pure water rising mains, feeder pipelines, overhead tank’s reservoirs, electromechanical works (p/m&allied works), 11kv express feeder main, a distribution network with house service connections etc and Operation and Maintenance (O&M) of five years.

End Date: April 10, 2023

Download PDF


Implementing Agency: Karnataka Urban Water Supply and Drainage Board (KUWSDB)

Segment: Water Supply

Work: The scope of work includes improvements of the water supply system to Gundlupet town including Operation and Maintenance (O&M) for a period of five years through design, build, operation and transfer (DBOT) mode under Atal Mission for Rejuvenation and Urban Transformation (AMRUT) 2.0 scheme.

End Date: March 6, 2023

Download PDF


Implementing Agency: Swachha Andhra Corporation (SAC)

Segment: Wastewater

Work: Investigation, survey and construction of sewage treatment plants (STPs) in different clusters of Andhra Pradesh. These clusters are:

Cluster 1 : It involves construction of 33 STPs having a total capacity of 45.38 million litre per day (mld) in Amadalavalasa, Ichapuram and Palasa Kasibugga urban local bodies (ULBs) of Srikakulam district and Palakonda, Parvathipuram and Salur ULBs of Manyam district at an estimated cost of Rs 0.76 billion.

Cluster 2 : It involves construction of 39 STPs having a total capacity of 47.17 mld in Rajam, Bobbili and Nellimarla ULBs of Vizianagaram district and Narispatnam, Yellamanchali and Tuni ULBs of Anakapalli district at an estimated cost of Rs 0.78 billion.

Cluster 3 : It involves construction of 17 STPs having a total capacity of 45.65 mld in Samalkot,  Pithapuram, Peddapuram , Gollaprollu and Yeleswaram ULBs of Kakinda district and Nidadavole and Kovvur ULBs of East Godavari at an estimated cost of Rs 0.75 billion.

Cluster 4 :  It involves construction of 11 STPs having a total capacity of 45.06 mld in Amalapuram, Ramachandrapuram, Mundapeta and Mumidivaram ULBs of Konaseema district and Palacole and Narsapur ULBs of West Godavari district at an estimated cost of Rs 0.74  billion.

Cluster 5 : It involves construction of 16 STPs having a total capacity of 50.047 mld in Tanuku ULB of West Godavari district and Jangareddy Gudem and Nuzivid ULBs of Eluru district and Pedana and Vuyyuru ULBs of Krishna district and Tiruvuru ULB of NTR district at an estimated cost of Rs 0.82 billion.

Cluster 6 : It involves construction of 11 STPs havinga total capacity of 49.7 mld in Jaggiahpet and Nandigama ULBs of NTR district and Macherla, Sattenapalli and Piduguralla ULBs of Palnadu district at an estimated cost of Rs 0.82 billion.

Cluster 7 : It involves construction of 10 STPs having a total capacity of 43.99 mld in Vinukonda ULB of Palnau district and Markapur, Giddalur, Chimakurthy and Kanigri ULBs of Prakasam district at an estimated cost of Rs 0.72 billion.

Cluster 8 : It involves construction of 11 STPS having a total capacity of 47.986 mld in Repalle, Bapatla, Chirala and Addanki ULBs of Baptla district and Ponnur ULB of Guntur district at an estimated cost of Rs 0.79 billion.

Cluster 9 : It involves construction of 11 STPs having a total quantity of 46.16 mld in Dhone, Atmakur, Nandikotkur and Allagadda ULBs of Nandyal district and Gudur ULB of Kurnool district and Jammalamadugu ULB of YSR Kadapa district at an estimated cost of Rs 0.76 billion.

Cluster 10 : It involves construction of 14 STPs having a total quantity of 43.6 mld in Badvel, Mydukur and Yerraguntla ULBs of YSR Kadapa district and Kandukur and Atmakur ULBs of SPS Nellore district at an estimated cost of  Rs 0.72 billion.

Cluster 11 : It involves construction of 8 STPs having a total capacity of 10.7 mld in Rayadurg, Gooty and Kalyandurgam ULBs of Ananthapur district and Kadiri, Madakasira and Puttaparthi ULBs of Sri Satya Sai district  at an estimated cost of Rs 0.82 billion.

Cluster 12 : It involves construction of 12 STPs having a total capacity of 47.07 mld in Gudur, Venkatagiri, Sullurpet and Naiduupet ULBs of Sri Balaji district and Rajampeta ULB of Annamaya district at an  estimated cost of Rs 0.77 billion.

Cluster 13 : It involves construction of 12 STPs having a total capacity of 42.816 mld in Puganur, Palamaneru, Nagari and Puttur ULBS of Chittoor district at an estimated cost of  Rs 0.71 billion.

End Date: May 1, 2023

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF

Download PDF


Implementing Agency: Shevgaon Municipal Council

Segment: Water Supply

Work: The scope of the project includes working survey, head works-approach channel of 1080 m, jackwell and overhead pump house of 9 m diametre, approach bridge of 25 m, raw water pumping machinery of 120 HP, P/L/L/J and hyd.testing of RWRM 450 mm dia DIK-9 pipes L- 19.800 km, conventional water treatment plant (WTP) Cap – 12 million litre per day (mld) with automation, pure water pumping machinery- 150 HP, P/L/L/J and hyd. testing of PWRM 400 mm dia DIK-9 pipes L- 4.00 km, P/L/L/J and hyd. testing of 200 to 500 mm DI K-7 pipe PWGM L6.334 km, master balancing reservoir (MBR) CUM elevated service reservoir (ESR)- cap- 11.85 lakh ltr st. ht-25m, ESR – 8.70 lakh ltr st. ht-15m, ESR cum wash water tank cap-5 lakh ltr st. ht-20m, ESR cap-1.60 lakh ltr st.ht-17m, distribution system L113.63 km and other miscellaneous work.

End Date: February 20, 2023

Download PDF


Implementing Agency: Public Health Engineering Department (PHED), Rajasthan

Segment: Water Supply

Work: The scope of the project includes water supply works in  Prithviraj Nagar and adjoining areas based on Bisalpur water supply including 10 years of operation and maintenance (O&M).

End Date: May 1, 2023

Download PDF


Implementing Agency: Uttar Pradesh Jal Nigam (UPJN)

Segment: Water Supply

Work: The scope of the projects include:

Group B: The scope of the project includes the construction of the overhead tank, CWR, pump house, laying and jointing rising main, the distribution system and tube-wells including programmable logic controller (PLC) supervisory control and data acquisition (SCADA) automation. It will also involve commissioning, testing, trial and run, defect liabilities and handling the complete works on a turn-key basis. The project will likely be completed in 24 months at an estimated cost of Rs 0.93 billion.

Group C: The scope of the project includes the construction of an overhead tank, CWR, pump house, laying and jointing rising main, the distribution system and tube-wells including programmable logic controller (PLC) supervisory control and data acquisition (SCADA) automation. It will also involve commissioning, testing, trial and run, defect liabilities and handling the complete works on a turn-key basis. The project will likely be completed in 24 months at an estimated cost of Rs 0.92 billion.

End Date: February 15, 2023

Download PDF

Download PDF


Implementing Agency: Bangalore Water Supply and Sewerage Board (BWSSB)

Segment: Wastewater

Work: The scope of work includes design and construction of new 150 million litre per day (mld) STP based on activated sludge process (ASP) with biological nutrient removal (BNR) system in place of the existing 180 mld STP at Vrishabhavathi Valley, Nayandanahalli with operation and maintenance (O&M) of five years on turnkey basis.

End Date: February 13, 2023

Download PDF


Implementing Agency: Bihar Urban Infrastructure Development Corporation Limited (BUIDCO)

Segment: Wastewater

Work: The scope of the project includes:

Motihari Sewerage (STP and I&D) Project: Design and construction of four sewage treatment plant (STP) of 4.6 million litre per day (MLD), 6.3 mld, 5.8 mld and 6.3 mld and allied works controlled with Supervisory Control And Data Acquisition (SCADA) including without fall drains of length 97 metre (m), 392 m, 75m, ad 72 m respectively, survey, design review, redesign where necessary, construction of three pumping stations including 5,713 m interception drain including screens and other works with operation and maintenance (O&M) of 15 years.

Daudnagar Sewerage(STP and I&D) Project: Design and construction of STP having a capacity of 10.5 mld along with all appurtenant structures controlled with SCADA, survey, design review, redesigning, construction of interception drain of 349 m and effluent channel disposal of treated effluent through pipeline with O&M of 15 years.

End Date: March 4, 2023

Download PDF

Download PDF


Implementing Agency: Public Health Engineering Department, Haryana

Segment: Wastewater

Work: The scope of work includes survey, study, investigation, detailed project report (DPR), detailed notice inviting tender (DNIT), construction supervision and contract management for works relating to water supply, sewerage, septage management, sewerage treatment plant (STP), refuse of treated wastewater for the towns of Ganaur, Kharkhoda, Gohana and Sonipat in Haryana.

End Date: February 10, 2023

Download PDF


Implementing Agency: Ambala Municipal Corporation (AMC)

Segment: Wastewater

Work: The scope of the project includes construction of sewerage system in deficit area including all ancillary works, pumping station and sewage treatment plant (STP) on sequential batch reactor (SBR) technology along with operation and management (O&M) for five years under Atal mission for rejuvenation and urban transformation (AMRUT) program.

End Date: February 21, 2023

Download PDF


Implementing Agency: Bagalakote Town Development Authority

Segment: Wastewater

Work: The scope of the project includes:

Package 1: Design and construction along with operation & maintenance (O&M) for 5 Years for layout development and infrastructure work consisting of roads, water distribution, ground service reservoirs, sewer Network, storm water drains (SWD), power supply system (HESCOM), ICT infrastructure system work, chain link fencing for parks / open areas, tree plantation for Sector B, C and D and primary drains outside Unit-3 area, along with Sewage Pumping Stations (SPS) (including pumping machinery and pumping mains for all sectors) for Bagalakote Navanagar – Unit 3 Area under Lumpsum Turnkey Contract. The estimated cost of package 1 is Rs 5,605.9 million.

Package 2: Design and construction along with O&M for 5 Years for layout development and infrastructure work consisting of roads, water distribution, ground service reservoirs, sewer network, SWD, power supply system (HESCOM), ICT infrastructure system work, chain link fencing for parks / open areas, Tree plantation for Sector A and E and approach roads connecting Unit-3 area roads and utility roads (connecting WTP & STP area), Water supply Transmission Network, On-grid Solar works for Bagalakote Navanagar – Unit 3 Area- under Lumpsum Turnkey Contract. The estimated cost of package 2 is Rs 4,894.3 million.

Package 3: Design and construction along with O&M for a Period of 5 Years for layout development and infrastructure works consisting of roads, water distribution, ground service reservoirs, sewer network, storm water drains, power supply system (HESCOM), ICT infrastructure system works, chain link fencing for parks / open areas, Tree plantation for Sector F, G and H for Bagalakote Navanagar – Unit 3 Area, under Lumpsum Turnkey Contract. The estimated cost of the project is Rs 4,711 million.

Package 4: Design and Construction along with O&M for a Period of 05 Years for layout development and infrastructure works consisting of roads, water distribution, ground service reservoirs, sewer network, SWD, Power Supply System (HESCOM), ICT infrastructure system works, Chain link fencing for Parks / open areas, Tree plantation for Sector I, J and K for Bagalakote Navanagar – Unit 3 Area, under Lumpsum Turnkey Contract. The estimated cost of the project is Rs 5,281 million.

End Date: February 15, 2023

Download PDF

Download PDF

Download PDF

Download PDF


Implementing Agency : Uttar Pradesh Jal Nigam (UPJN)

Segment: Wastewater

Work : The scope of the project includes survey, soil investigation, supply, laying, jointing, testing and commissioning of sewer line by open cut and trenchless method as required with apparent works, construction of 68 million litre per day (mld) sewage treatment plant (STP) based on SBR technology, MPS (well sinking method) with the civil structure for 71.17 mld average flow for ultimate year including all electromagnetic works, rising main, 5 STPs IPS having capacity of 20.13 mld, 7.28 mld, 1.5 mld, 11.32 mld and 58.72 mld and all other appurtenant works followed by three months trial and run of all executed works in different wards of Karhera Zone.

End Date: April 18, 2023

Download PDF


Implementing Agency: Karnataka Urban Water Supply and Drainage Board

Segment: Wastewater

Work: The scope of the project includes providing UGDS to Hukkeri town including Operation and Maintenance (O&M) for a period of 3 Years Including 1 Year defect liability period (DLP) through design, built, operation and transfer (DBOT) Mode.

End Date: April 26, 2023

Download PDF


Implementing Agency: Municipal Corporation of Greater Mumbai (MCGM)

Segment:  Wastewater

Work: The scope of the project includes rehabilitation of 600 mm to 900 mm diameter sewer lines by trenchless technology in different areas of Mumbai, Maharashtra.

End Date: February 28, 2023

Download PDF


Implementing Agency: Madhya Pradesh Urban Development Company Limited (MPUDCL)

Segment: Wastewater

Work: The scope of the project includes design, supply, construction, testing, commissioning and operation and maintenance of sewerage system, providing house sewer connections for the households to collect and convey the sewage and providing sewage treatment facility prior to discharge into nearby water body.

End Date: March 28, 2023

Download PDF


Implementing Agency :  Maharashtra Jeevan Pradhikaran (MJP)

Segment: Water Supply

Work: The scope of the project includes designing, providing, erecting, commissioning and testing raw water and pure water pumping machinery and automation system with five years of operation and maintenance (O&M).

End Date: February 10, 2023

Download PDF


Implementing Agency : Water Resources Department, Rajasthan

Segment: Water Supply

Work: The scope of the project includes the construction of the Kaliteer Lift Scheme in Dholpur under Engineering, Procurement and Construction (EPC) basis (single responsibility turn-key basis) and its operation and maintenance (O&M) for 8 years.

End Date: March 8, 2023

Download PDF


Implementing Agency : Maharashtra Jeevan Pradhikaran (MJP)

Segment: Water Supply

Work: The scope of the project includes designing, providing, erecting, commissioning and testing raw water and pure water pumping machinery and automation system with five years of operation and maintenance (O&M).

End Date: March 30, 2023

Download PDF


Implementing Agency : Faridabad Municipal Corporation

Segment: Wastewater

Work: Project management consultancy (PMC) for revamping of sewerage system in Faridabad (Phase – I) including rehabilitation of the existing lines using cured-in-place pipe (CIPP) liner.

End Date: January 26, 2023

Download PDF


Implementing Agency : Faridabad Municipal Corporation

Segment: Wastewater

Work: The scope of the project includes revamping of sewerage system in Faridabad (Phase – I) including rehabilitation of the existing lines using cured-in-place pipe (CIPP) liner.

End Date: March 29, 2023

Download PDF


Implementing Agency : Bihar Urban Infrastructure Development Corporation Limited (BUIDCO)

Segment: Wastewater

Work: The scope of the project includes:

-Construction of two STP of installed capacity of 4.5 million litres per day (mld) before the aqueduct and 4.5 mld after the aqueduct along with all appurtenant structures and allied works controlled with Supervisory Control And Data Acquisition (SCADA) including 460 m approach road.

-Survey, design review, redesign where necessary, and building 1.95 km interception drain before aqueduct & 2.1 km interception drain after aqueduct for the tapping of 37 drains, including screens and mechanically operated gates facilitating surface water runoff into Ramrekha river.

-Operation and maintenance (O&M) of the complete works of the STP, interception & diversion (I&D) works, and effluent channel for a period of 15 years in Ramnagar town.

End Date: February 10, 2023

Download PDF


Implementing Agency : Municipal Corporation of Greater Mumbai (MCGM)

Segment: Wastewater

Work: Appointment of a consultant to study the feasibility of integrating potable water produced from seven Waste Water Treatment Facilities(WWTF) in Versova, Bhandup, Dharavi, Bandra, Worli, Malad and Ghatkopar with water supply system of Mumbai City under the Mumbai Sewerage Disposal Project Stage II

End Date: February 13, 2023

Download PDF


Implementing Agency : Sangli Miraj and Kupwad City Municipal corporation (SMKC)

Segment: Wastewater

Work: The scope of the work includes a working survey, construction of a collection system, wet well, panel rooms, pumping machinery, pumping main, 27 million litres per day (mld) Sewage treatment plant (STP) with Sequential Batch Reactor (SBR) technology, remaining works of Sangli and Miraj UGD and other miscellaneous works.

End Date:  February 7, 2023

Download PDF


Implementing Agency: Rajasthan Urban Drinking Water Sewerage & Infrastructure Corporation Limited (RUDSICO)

Segment : Water Suppluy, Wast water

Work : The scope of the project include :

Barmer : It involves development of sewerage network with house connections, upgradation of existing 10 million litre per day (mld) sewage treatment plant (STP), waste stabilisation pond (WSP) and all allied works and operation services of the upgradation units of STP for 10 years.

Baltora : It involves development of water supply network improvements with house service connections for non-revenue water reduction and continuous water supply and providing sewer network with house connections and allied works and operation services of the entire water system for 10 years.

End Date : January 30, 2023

Download PDF


Implementing Agency : Bihar Urban Infrastructure Development Corporation Limited (BUIDCO)

Segment : Wastewater

Work : Development of Serpentine Nala in Patna, Bihar.

End Date : February 10, 2023

Download PDF


Implementing Agency : Shimla Jal Prabandhan Nigam Limited (SJPNL)

 Segment : Waste water

Work : The scope of the project includes expansion and extension of sewerage network to unserved areas for Lapani zone sewage treatment plant (STP) at a cost of Rs 570.34 million and Summerhill Zone STP at a cost of Rs 112.4 million in Shimla.

End date : February 20, 2023

Download PDF


Implementing Agency : Water Resources Department (WRD), Goa

Segment : Water supply

Work : Construction of barrage across Chapora river at Sal.

End date : January 27, 2023

Download PDF


Implementing Agency : Water Resources Department (WRD), Goa

 Segment :  Watersupply

Work : Construction of Pump House along with Pump and Accessories, Transformer Substation at Sal and providing and Laying 1200 mm Dia DI Rising main from Sal to Amthane and construction of Break Pressure Tank.

End date : February 7, 2023

Download PDF


Implementing Agency : Water Resources Department (WRD), Goa

Segment : Water Supply

Work : Construction of Pump House along with Pump and Accessories, Transformer Substation at Amthane and providing & Laying 1200mm Dia DI Rising main from Amthane to Dhangarwada and Gravity main from Dhangarwada to LBMC and construction of Break Pressure Tank.

End date : February 1, 2023

Download PDF


Implementing Agency : Pune Municipal Corporation (PMC)

Segment : Water supply

Work :The scope of work includes transmission, storage and distribution of clear water in Mahalunge and Sus village of PMC.

End date : February 2, 2023

Download PDF


Implementing Agency : Bihar Urban Infrastructure Development Corporation Limited (BUIDCo)

Segment : Wastewater

Work: The project involves design and build three STPs of installed capacity 9 million litre per day (mld), 2 mld and 1.1 mld and all appurtenant structures and allied works including staff quarters, treated effluent channel for disposal, controlled with supervisory control and data acquisition (SCADA) in Supaul, Bihar

-Survey, review the designs, redesign where necessary, and build new 6 nos interception and diversion (I&D) structures for the drains, and all appurtenant structures and allied works including gravity main, rising main and effluent channel including controlled with SCADA and operation and maintenance (O&M) for a period of 15 years.

End Date : February 17, 2023

Download PDF


Implementing Agency : Bihar Urban Infrastructure Development Corporation Limited (BUIDCo)

Segment : Wastewater

Work : The project involves design and build  STP of installed capacity 6 mld and all appurtenant structures and allied works including mps, staff quarters, uv disinfection and effluent channel for disposal controlled with SCADA in Khalgaon, Bihar.

-Survey, review the designs, redesign where necessary, and build new 4 nos I&D structures for the drains controlled with SCADA including survey, design, construction of 4  pumping stations and all appurtenant structures and allied works with O&M for a period of 15 years.

End Date : February 17, 2023

Download PDF


Implementing Agency : Chennai Petroleum Corporation Limited (CPCL)

Segment :  Wastewater

Work : The scope of the project include project management, residual process design and detailed engineering, procurement, fabrication, inspection, supply, manufacture, transportation of all equipment/materials to the work site and storage at site, assembly, erection and installation, construction and erection of civil and structural, mechanical, electrical, instrumentation and piping works, acid /alkali resistant proof tiling, painting, testing, pre-commissioning, trial run for 30 days before commissioning, commissioning, 3D modeling, Hazard and Operability Analysis (HAZOP), training of CPCL’s personnel; performance guarantee test run for 72 hours continuous operation , guaranteeing and handing over of ETP and solid waste handling facilities to CPCL on lump sum turnkey basis as per design basis, scope of work/supply, equipment list, standards, p&ids, data sheets, drawings, etc., all complete within contractor’s specified battery limits including supply of spares, chemicals & consumables. the epc contractor shall be required to obtain all statuary approvals for completion of his scope of work. The scope also includes operation and maintenance of the ETP for a period of 3 years which shall start from the date of end of successful commissioning.

End Date : June 14, 2023

Download PDF


Implementing Agency : Public Health Engineering Department (PHED), Rajasthan

Segment : Water Supply

Work : The scope of work includes all works required for delivering water, through distribution pipeline network of the project area and to provide sufficient extensions of this system to add new supply zones to the system in future. It also included operation and maintenance (O&M) for 10 years after defect liability period (DLP) of one year to deliver designed quantity of water at various head works, OHSRs and to regulate supply as per notified flows during O&M time.

End Date: January 30, 2023

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water Supply

Work: The scope of the project includes surveying, planning, designing, delivery, erection, construction, commissioning and completion in all respect of all Civil, Electrical and Mechanical Works including all allied, related and enabling works for the proposed water supply scheme based on surface water of open cast stone mine/pond in Chianbera and Dharampura.

End Date: April 19, 2023

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water Supply

Work : The project involves sinking of tube well, construction of different capacity reinforced cement concrete (RCC) over head reservoir over pile /raft foundation including sub soil investigation works with laying distribution system, pump house and providing functional household tap connection (61964 nos) for 38 nos pipe water supply scheme including two years O&M in Patashpur-I, Patashpur-II, Egra-I and Deshapran Block under Tamluk division in Purba Medinipur district.

End date : March 10, 2023

Download PDF


Implementing Agency: Faridabad Municipal Corporation

Segment: Wastewater

Work: Project management consultancy (PMC)  for the rehabilitation of the Sewerage system (Phase -I) in Faridabad, Haryana

End Date: February 28, 2023

Download PDF


Implementing Agency: West Bengal Public Health Engineering Department (PHED)

Segment: Water Supply

Work : Sinking of tube well, construction of different capacity rcc over head reservoir over pile / raft foundation including sub soil investigation works with laying distribution system, pump house and providing functional household tap connection (41827 nos), etc. for 32 nos pipe water supply scheme. The project is likely to be completed in 10 months at an estimated cost of Rs 1.21 billion.

End date : February 10, 2023

Download PDF


Implementing Agency: Municipal Corporation of Greater Mumbai (MCGM)

Segment: Wastewater

Work: The scope of the project includes design, construction, operation and maintenance (O&M) of 12 million litre per day (mld) ATTP on pilot basis for recycle and reuse of water for direct potable purposes at Colaba wastewater reuse treatment facility with O&M period of 15 years on design, build and operate (DBO) model.

End date : Cancelled

Download PDF


Implementing Agency : Public Health Engineering Department (PHED)

Segment  : Water Supply

Work : The project involves sinking of tube well, construction of different capacity reinforced cement concrete (RCC) over head reservoir over pile /raft foundation including sub soil investigation works with laying distribution system, pump house and providing functional household tap connection (32862 Nos) for 21 nos pipe water supply scheme including two years operation and maintenance (O&M) in Moyna and Contai -I block Under Tamluk Division in Purba Medinipur District.

End date : Cancelled

Download PDF