About 30 to 50 per cent work has been completed on seven waste water treatment facilities (WWTF) under Stage II of Mumbai Sewerage Disposal Project.
Versova WWTF: The scope of work involves design and construction of 180 million litre per day (mld) WWTF including 90 mld tertiary treatment facility and space reservation for 60 mld, total comprises of 240 mld on lump sum basis. The contract period is 48 months.
Bhandup WWTF: The scope of work involves design and construction of 215 mld capacity WWTF at Bhandup. The contract period is 48 months.
Ghatkopar WWTF: The scope of work involves design and construction of 337 mld capacity WWTF at Ghatkopar. The contract period is 48 months.
Dharavi WWTF: The scope of work involves design and construction of 418 mld capacity WWTF including the 209 mld tertiary treatment facility. The contract period is 60 months.
Bandra WWTF : The scope of work involves design and construction of 360 mld capacity WWTF at Bandra. The contract period is 60 months.
Worli WWTF : The scope of work involves design and construction of 500 mld capacity WWTF at Worli. The contract period is 60 months.
Malad WWTF : The scope of work involves design and construction of 454 mld WWTF including 227 mld tertiary treatment facility.
The project includes an operation and maintenance (O&M) period of 15 years.
The work is likely to be completed by mid 2026.